This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Wisconsin Public Service Corporation, Wisconsin Power and Light Company, and Madison Gas and Electric Company; (Kewaunee Nuclear Power Plant, Unit No. 1); Order Approving Transfer of Operating Authority and Conforming Amendment
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Related Documents
Enhanced Content - Related Documents
FederalRegister.gov uses the agency dockets published with the document to display related documents.
Wisconsin Public Service Corporation, Wisconsin Power and Light Company, and Madison Gas and Electric Company; (Kewaunee Nuclear Power Plant, Unit No. 1); Order Approving Transfer of Operating Authority and Conforming Amendment
Wisconsin Public Service Corporation, Wisconsin Power and Light Company, and Madison Gas and Electric Company; (Kewaunee Nuclear Power Plant, Unit No. 1); Order Approving Transfer of Operating Authority and Conforming Amendment
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
9
as of
11/17/2026 at 2:15 pm EST
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
I.
Wisconsin Public Service Corporation (WPSC), Wisconsin Power and Light Company (WP&L), and Madison Gas and Electric Company (MGE) (the licensees), are the holders of Facility Operating License No. DPR-43, which authorizes operation of Kewaunee Nuclear Power Plant, Unit No. 1 (Kewaunee or the facility). The facility is located at the licensees' site in Kewaunee County, Wisconsin. The license authorizes the licensees to possess, use, and operate Kewaunee.
II.
By application dated November 24, 1999, as supplemented December 7, 1999, and February 8, 2000, the Commission was informed that WPSC, on behalf of itself and WP&L and MGE, entered into operating service agreements with Nuclear Management Company, LLC (NMC). The initial application and the supplements are hereinafter referred to as “the application” unless otherwise indicated. Under the proposed transaction, NMC will be designated as the exclusive licensee authorized to use and operate Kewaunee in accordance with the terms and conditions of the license. The transaction involves no change in plant ownership. WPSC requested approval of the proposed transfer of operating authority under the Kewaunee facility operating license to NMC. The application also requested a conforming amendment to reflect the transfer. The proposed amendment would add NMC to the license as the licensee authorized to use and operate Kewaunee, and make changes to the license to reflect that the current licensees no longer have operating authority.
According to the application for approval filed by WPSC, NMC would become the licensee authorized to use and operate Kewaunee following approval of the proposed license transfer. NMC will assume exclusive responsibility for the operation and maintenance of Kewaunee. Ownership of Kewaunee will not be affected by the proposed transfer of operating authority. WPSC, WP&L, and MGE will retain their current ownership interest. NMC will not own any portion of Kewaunee. Likewise, the licensees' entitlement to capacity and energy from Kewaunee will not be affected by the transfer of operating authority. No physical changes to the Kewaunee facility were proposed in the application.
Approval of the transfer of operating authority under the facility operating license and conforming license amendment was requested by WPSC pursuant to 10 CFR 50.80 and 50.90. Notice of the application for approval and an opportunity for a hearing was published in the
Federal Register
on February 4, 2000 (65 FR 5706). No hearing requests or written comments were received.
Pursuant to 10 CFR 50.80, no license, or any right thereunder, shall be transferred, directly or indirectly, through transfer of control of the license, unless the Commission shall give its consent in writing. Upon review of the information in the application by WPSC, and other information before the Commission, and relying upon the representations and agreements contained in the application, the NRC staff has determined that NMC is qualified to hold the operating authority under the license and that the transfer of the operating authority under the license to NMC is otherwise consistent with applicable provisions of law, regulations, and orders issued by the Commission, subject to the conditions set forth below. The NRC staff has further found that the application for the proposed license amendment complies with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter 1; the facility will operate in conformity with the application, the provisions of the Act and the rules and regulations of the Commission; there is reasonable assurance that the activities authorized by the proposed license amendment can be conducted without endangering the health and safety of the public and that such activities will be conducted in compliance with the Commission's regulations; the issuance of the proposed license amendment will not be inimical to the common defense and security or the health and safety of the public; and the issuance of the proposed amendment will be in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied. The foregoing findings are supported by a Safety Evaluation dated May 15, 2000.
III.
Accordingly, pursuant to Sections 161b, 161i, and 184 of the Atomic Energy Act of 1954, as amended, 42 U.S.C. 2201(b), 2201(i), and 2234, and 10 CFR 50.80,
It is hereby ordered
that the transfer of operating authority under the license as described herein to NMC is approved, subject to the following conditions:
(1) After receipt of all required regulatory approvals of the transfer of operating authority to NMC, WPSC and NMC shall inform the Director of the Office of Nuclear Reactor Regulation in writing of such receipt within 5 business days and of the date of the closing of the transfer no later than 7 business days before the date of closing. If the transfer is not completed by April 1, 2001, this Order shall become null and void, provided, however, upon written application and for good cause shown, such date may in writing be extended.
(2) NMC shall, prior to completion of the transfer of operating authority of Kewaunee, provide the Director of the Office of Nuclear Reactor Regulation satisfactory documentary evidence that NMC has obtained the appropriate amount of insurance required of licensees under 10 CFR Part 140 of the Commission's regulations.
It is further ordered
that consistent with 10 CFR 2.1315(b), a license amendment that makes changes, as
( printed page 31942)
indicated in Enclosure 2 to the cover letter forwarding this Order, to conform the license to reflect the subject transfer of operating authority is approved. The amendment shall be issued and made effective at the time the proposed transfer is completed.
This Order is effective upon issuance.
For further details with respect to this action, see the initial application dated November 24, 1999, and supplements dated December 7, 1999, and February 8, 2000, and the safety evaluation dated May 15, 2000, which are available for public inspection at the Commission's Public Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, and accessible electronically through the ADAMS Public Electronic Reading Room link at the NRC Web site (http://www.nrc.gov).
Dated at Rockville, Maryland, this 15th day of May 2000.
For the Nuclear Regulatory Commission.
Brian W. Sheron,
Acting Director, Office of Nuclear Reactor Regulation.