This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Proposed Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Interested parties should submit comments in writing on or before September 25, 2000 to be considered in the formulation of a final rule.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
33
as of
11/16/2026 at 10:15 am EST
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCIES:
Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).
ACTION:
Proposed rule.
SUMMARY:
The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) are proposing to amend the Federal Acquisition Regulation (FAR) to explicitly state the right of the contracting officer to unilaterally determine the final contract payment amount when the contractor does not submit the final invoice or voucher within the time specified in the contract. This contracting officer decision is final and binding upon the contractor and will not be subject to the right of appeal under the Contract Disputes Act.
DATES:
Interested parties should submit comments in writing on or before September 25, 2000 to be considered in the formulation of a final rule.
ADDRESSES:
Submit written comments to: General Services Administration, FAR Secretariat (MVRS), 1800 F Street, NW, Room 4035, ATTN: Laurie Duarte, Washington, DC 20405.
Please submit comments only and cite FAR case 1999-026 in all correspondence related to this case.
FOR FURTHER INFORMATION CONTACT:
The FAR Secretariat, Room 4035, GS Building, Washington, DC, 20405, at (202) 501-4755 for information pertaining to status or publication schedules. For clarification of content, contact Ms. Linda Klein, Procurement Analyst, at (202) 501-3775. Please cite FAR case 1999-026.
SUPPLEMENTARY INFORMATION:
A. Background
The Department of Defense established the Contract Close-out Working Integrated Process Team (CCWIPT) to improve the contract closeout process and reduce associated paperwork. On April 7, 1999, the team issued a report with a number of recommendations. The report found that the leading reason for contracts to remain open after they are physically complete is the contractor's failure to submit a final voucher to the Government. Therefore, one of the CCWIPT's recommendations is to revise the FAR to indicate that if a contractor has failed to submit any final invoice or voucher for a physically completed contract within the time provided, the contractor shall not have the right to appeal under the Disputes Clause at FAR 52.233-1, Disputes, any determination made by the contracting officer regarding the amount of final payment.
The Councils have adopted the CCWIPT's recommendation in this proposed rule. The rule revises FAR 42.705, Final indirect cost rates, and FAR 52.216-7, Allowable Cost and Payment, to—
Explicitly state that the contracting officer may issue a unilateral modification that reflects the contracting officer's determination of the amounts due to the contractor under a completed contract. The contracting officer may make this determination if the contractor fails to submit a completion invoice or voucher within the time specified (normally 120 days after settlement of the final indirect cost rates but may be longer, if approved in writing by the contracting officer); and
Make the contracting officer's determination not subject to appeal under the Disputes Clause of the contract.
This rule was not subject to Office of Management and Budget review under Section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
B. Regulatory Flexibility Act
The Councils do not expect this proposed rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601,
et seq., because it is unlikely that a contractor would appeal the contracting officer's determination. The contractor would have little left to dispute regarding the amount of final payment on the contract once the contractor has submitted a final indirect cost rate proposal, the auditor has completed a final incurred cost audit; and the contractor and the Government have negotiated and agreed to the final indirect rates. An Initial Regulatory Flexibility Analysis has, therefore, not been performed. We invite comments from small businesses and other interested parties. The Councils will consider comments from small entities concerning the affected FAR parts in accordance with 5 U.S.C. 610. Interested parties must submit such comments separately and should cite 6 U.S.C. 601,
et seq.
(FAR case 1999-026), in correspondence.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the proposed changes to the FAR do not impose information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501,
et seq.
(b) Within 120 days (or longer period, if approved in writing by the contracting officer,) after settlement of the final annual indirect cost rates for all years of a physically complete contract, the contractor shall submit a completion invoice or voucher reflecting the settled amounts and rates.
(c)(1) If the contractor fails to submit a completion invoice or voucher within the time specified in paragraph (b) of this section, the contracting officer may—
(i) Determine the amounts due to the contractor under the contract; and
(ii) Record this determination in a unilateral modification to the contract.
(2) This contracting officer determination is—
(i) Final and binding upon the contractor in discharge of all obligations to the contractor arising under the contract; and
(ii) Not subject to the right of appeal under the Disputes clause.
( printed page 46333)
PART 52—SOLICITATION PROVISIONS AND CONTRACT CLAUSES
3. Amend Section 52.216-7 by revising the date of the clause; in paragraph (d) by redesignating paragraph (d)(4) as (d)(5) and paragraph (d)(5) as (d)(4), respectively; revising the newly designated (d)(5); by adding paragraph (d)(6); and by amending paragraph (h)(1) by removing “paragraph (d)(4)” and adding, in its place, “paragraph (d)(5)”. The revised text reads as follows:
(5) Within 120 days (or longer period, if approved in writing by the Contracting Officer,) after settlement of the final annual indirect cost rates for all years of a physically complete contract, the Contractor shall submit a completion invoice or voucher to reflect the settled amounts and rates.
(6)(i) If the Contractor fails to submit a completion invoice or voucher within the time specified in paragraph (d)(5) of this clause, the Contracting Officer may—
(A) Determine the amounts due to the Contractor under the contract; and
(B) Record this determination in a unilateral modification to the contract.
(ii) This Contracting Officer determination is—
(A) Final and binding upon the Contractor in discharge of all obligations to the Contractor arising under the contract; and
(B) Not subject to the right of appeal under the Disputes clause.