Skip to Content

Notice

Electrical Interconnection of the Satsop Combustion Turbine Project

Document Details

Information about this document as published in the Federal Register.

Published Document

This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Start Preamble

AGENCY:

Bonneville Power Administration (BPA), Department of Energy (DOE).

ACTION:

Notice of availability of Record of Decision (ROD).

SUMMARY:

This notice announces the availability of the ROD to offer contract terms to integrate power from the Satsop Combustion Turbine Project, a 650-megawatt gas-fired, combined-cycle, combustion turbine power generation project, into the Federal Columbia River Transmission System (FCRTS). The project is located in Satsop, in the Satsop Development Park, in Grays Harbor County, Washington. This decision was reached after consideration of the site-specific potential environmental impacts analyzed in BPA's Resource Contingency Program Environmental Impact Statement (RCP EIS, DOE/EIS-0230, November 1995), and is consistent with BPA's Business Plan EIS (BP EIS, DOE/EIS-0183, June 1995), and Business Plan ROD (August 1995).

ADDRESSES:

Copies of the ROD for the Electrical Interconnection of the Satsop Combustion Turbine Project may be obtained by calling BPA's toll-free document request line: 1-800-622-4520. The RCP EIS, BP EIS, and BP ROD are also available.

Start Further Info

FOR FURTHER INFORMATION CONTACT:

Dawn R. Boorse, Bonneville Power Administration—KEC-4, P.O. Box 3621, Portland, Oregon, 97208-3621, direct telephone 503-230-5678; toll-free telephone 1-800-282-3713; e-mail drboorse@bpa.gov.

Start Signature

Issued in Portland, Oregon, on April 30, 2002.

Steven G. Hickok,

Acting Administrator and Chief Executive Officer.

End Signature End Further Info End Preamble

[FR Doc. 02-11397 Filed 5-7-02; 8:45 am]

BILLING CODE 6450-01-P