Skip to Content

Rule

Defense Federal Acquisition Regulation Supplement; Protests, Disputes, and Appeals (DFARS Case 2003-D010)

Document Details

Information about this document as published in the Federal Register.

Published Document

This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Start Preamble

AGENCY:

Defense Acquisition Regulations System, Department of Defense (DoD).

ACTION:

Final rule.

SUMMARY:

DoD has issued a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to update text addressing procedures for processing of contractor claims submitted under DoD contracts. The rule removes obsolete text and relocates text to the DFARS companion resource, Procedures, Guidance, and Information.

EFFECTIVE DATE:

February 12, 2007.

Start Further Info

FOR FURTHER INFORMATION CONTACT:

Ms. Felisha Hitt, Defense Acquisition Regulations System, OUSD(AT&L)DPAP(DARS), IMD 3C132, 3062 Defense Pentagon, Washington, DC 20301-3062. Telephone (703) 602-0310; facsimile (703) 602-0350. Please cite DFARS Case 2003-D010.

End Further Info End Preamble Start Supplemental Information

SUPPLEMENTARY INFORMATION:

A. Background

This final rule—

  • Removes text at DFARS 233.204 regarding research of a contractor's history of filing claims during a contracting officer's review of a current claim. Text on this subject has been relocated to the DFARS companion resource, Procedures, Guidance, and Information (PGI) at http://www.acq.osd.mil/​dpap/​dars/​pgi;​ and
  • Revises DFARS 233.210 to remove an obsolete cross-reference and to add a reference to the guidance added to PGI regarding review of a contractor's claim.

DoD published a proposed rule at 71 FR 34867 on June 16, 2006. The proposed rule had provided for total elimination of the text at DFARS 233.204 and 233.210. One source submitted comments on the proposed rule, recommending that, instead of total elimination, the text at DFARS 233.204 should be relocated to PGI. DoD has adopted this recommendation and has included the corresponding changes in the final rule.

This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993.

B. Regulatory Flexibility Act

DoD certifies that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because the rule makes no significant change to DoD policy regarding consideration of claims submitted by contractors.

C. Paperwork Reduction Act

The Paperwork Reduction Act does not apply, because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

Start List of Subjects

List of Subjects in 48 CFR Part 233

End List of Subjects Start Signature

Michele P. Peterson,

Editor, Defense Acquisition Regulations System.

End Signature Start Amendment Part

Therefore,

End Amendment Part Start Part

PART 233—PROTESTS, DISPUTES, AND APPEALS

End Part Start Amendment Part

1. The authority citation for

End Amendment Part Start Authority

Authority: 41 U.S.C. 421 and 48 CFR Chapter 1.

End Authority
[Removed]
Start Amendment Part

2. Section 233.204 is removed.

End Amendment Part Start Amendment Part

3. Section 233.210 is revised to read as follows:

End Amendment Part
Contracting officer's authority.

See PGI 233.210 for guidance on reviewing a contractor's claim.