This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This notice initiates the public scoping process for the SEIS. Comments on issues may be submitted in writing until August 28, 2009. The date(s) and location(s) of any scoping meetings will be announced at least 15 days in advance through local news media, newspapers and the BLM Web site at: http://www.blm.gov/nv/st/en/fo/ely_field_ office.html. In order to be included in the draft SEIS, all comments must be received prior to the close of the scoping period or 15 days after the last public meeting, whichever is later. We will provide additional opportunities for public participation upon publication of the draft SEIS.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
20
as of
08/07/2026 at 2:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Bureau of Land Management, Interior.
ACTION:
Notice of Intent.
SUMMARY:
In compliance with the National Environmental Policy Act of 1976 (NEPA), as amended, and the Federal Land Policy and Management Act of 1976 FLPMA, as amended, the Bureau of Land Management (BLM) Ely and Southern Nevada District Offices intend to prepare a Supplemental Environmental Impact Statement (SEIS) for a proposed 500 kilovolt (kv) transmission line and associated facility from Ely, Nevada, to the Harry Allen substation just north of Las Vegas, Nevada and by this notice are announcing the beginning of the scoping process to solicit public comments and identify issues.
DATES:
This notice initiates the public scoping process for the SEIS. Comments on issues may be submitted in writing until August 28, 2009. The date(s) and location(s) of any scoping meetings will be announced at least 15 days in advance through local news media, newspapers and the BLM Web site at:
http://www.blm.gov/nv/st/en/fo/ely_field_office.html.
In order to be included in the draft SEIS, all comments must be received prior to the close of the scoping period or 15 days after the last public meeting, whichever is later. We will provide additional opportunities for public participation upon publication of the draft SEIS.
ADDRESSES:
You may submit comments related to the Proposed One Nevada Transmission Line by any of the following methods:
Mail:
BLM, Ely District Office, 702 North Industrial Way, Ely, NV 89301; or
Mail:
Southern Nevada District Office, 4701 North Torrey Pines Drive, Las Vegas, NV 89130.
Documents pertinent to this proposal may be examined at the Ely and Southern Nevada District Offices.
FOR FURTHER INFORMATION CONTACT:
For further information and/or to have your name added to our mailing list, send requests to: ATTN: One Nevada Transmission Line; contact Michael Dwyer, telephone (702) 821-7102; address, Ely District Office, 702 North Industrial Way, Ely, NV 89301; e-mail
michael_dwyer@blm.gov.
SUPPLEMENTARY INFORMATION:
On June 5, 2006 the applicant, Sierra Pacific Power Company (SPPC), requested authorization for the Ely Energy Center (EEC), a proposed power-generating facility that included rail lines, transmission lines with fiber optic cable, new and expanded substations, water well-fields and pipeline delivery systems, and associated facilities to be located on mostly public lands in White Pine, Lincoln, Nye, Elko, and Clark counties, Nevada. On January 26, 2007, the BLM published a Notice of Intent to prepare an EIS for the EEC and its associated facilities. Five public scoping meetings were held between February 5 and 9, 2007 in Las Vegas, Alamo, Ely, Elko, and Reno, Nevada. In January 2009, the BLM published a Notice of Availability of a draft EIS initiating a 90-day public comment period on the draft EIS. In February 2009, during the public comment period, NV Energy (formerly SPPC) made public its intention to postpone indefinitely the power generation facilities associated with the EEC from its proposal. On March 30, 2009, the BLM received an amended application and Plan of Development from NV Energy for one approximately 236-mile 500 kV transmission line, one new substation, an expansion of one substation, one fiber optic line, and related appurtenances that were part of the EEC proposal. The project was given a new name by the proponent: The One Nevada 500 kV Transmission Line Project (ON Line Project).
The BLM will develop a SEIS for the project because of substantial changes to the proposed action that are relevant to environmental concerns. See 40 CFR 1502.9(c). Removal of the coal-fired power generation facilities from the application makes an assessment of their impacts in the draft EIS no longer applicable.
The purpose of the public scoping process is to determine relevant issues that will influence the scope of the environmental analysis, including alternatives, and guide the process for developing the EIS. This scoping process will direct the preparation of a SEIS for a proposed 500 kv transmission line and associated facilities from Ely, Nevada, to the Harry Allen substation just north of Las Vegas, Nevada. The SEIS will supplement the Draft Environmental Impact Statement (EIS) for the Ely Energy Center. A power
( printed page 37729)
generation plant is not associated with the SEIS.
Because the ON line proposed action is part of the EEC proposed action, the ON Line SEIS will incorporate all applicable sections of the draft EIS. The ON Line draft SEIS will be made available for public comment, and applicable comments collected during the public comment period on the EEC draft EIS will be carried forward into the SEIS process. The BLM will use and coordinate the NEPA commenting process to satisfy the public involvement requirements of Section 106 of the National Historic Preservation Act (NHPA) (16 U.S.C. 470f) as provided for in 36 CFR 800.2(d)(3). Native American Tribal consultations will be conducted in accordance with policy, and Tribal concerns will be given due consideration, including impacts on Indian trust assets. Federal, State, and local agencies, as well as individuals or organizations that may be interested or affected by the BLM's decision on this project are invited to participate in the scoping process and, if eligible, may request or be requested by the BLM to participate as a cooperating agency. Before including your address, phone number, email address, or other personal identifying information in your comment, you should be aware that your entire comment—including your personal identifying information—may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information from public review, we cannot guarantee that we will be able to do so.