This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
72
as of
08/11/2026 at 2:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Bureau of Land Management, Interior.
ACTION:
Notice of availability.
SUMMARY:
The Bureau of Land Management (BLM) announces the availability of the Record of Decision (ROD) to authorize the granting of Rights-of-Way (ROW) for the construction of the One Nevada Transmission Line (ON Line) Project. Lands described in the ROW authorizations are located within the BLM Ely District Office's management area in White Pine, Nye, and Lincoln counties, Nevada; and the BLM Southern Nevada District in Clark County, Nevada. The Ely District Office was designated the project lead by the BLM Nevada State Director. The Ely District Manager has signed the ROD, which constitutes the final decision of the BLM. The appeal period for this decision will end 30 days after publication of this notice in accordance with 43 CFR 4.411(a).
ADDRESSES:
Printed copies of the ROD or electronic files on compact disk are available upon request from the Field Manager, Egan Field Office, Bureau of
( printed page 14987)
Land Management, HC 33 Box 33500, Ely, Nevada 89301. The ROD is also available at the following Web site:
http://www.blm.gov/nv/st/en/fo/ely_field_office.
Printed copies of the ROD are available for public inspection at several locations listed in the
SUPPLEMENTARY INFORMATION
section of this notice.
A limited number of copies of the document will be available at the following BLM offices:
—Las Vegas District Office, 4701 North Torrey Pines, Las Vegas, Nevada;
—Ely District Office, 702 North Industrial Way, Ely, Nevada; and
—Nevada State Office, 1340 Financial Boulevard, Reno, Nevada.
Printed copies of the ROD are available for public inspection at the following locations:
—University of Nevada-Reno, Getchell Library, Government Publication Dept., Reno, Nevada;
—Washoe County Library, 301 South Center Street, Reno, Nevada;
—White Pine County Library, 950 Campton Street, Ely, Nevada;
—Nye County Library, 167 S. Central Street, Tonopah, Nevada;
—Lincoln County Library, 63 Main Street, Pioche, Nevada; and
—Clark County Library, 1401 E. Flamingo Rd., Las Vegas, Nevada.
The main issues addressed in the Final EIS were visual resources, biological resources, lands with wilderness characteristics, and socioeconomic effects. Three alternatives were analyzed in the Final EIS: (1) The Proposed Action, in which the power line would be located largely within West-Wide Energy Corridors; (2) an alternative alignment within the corridors; and (3) no Action, which would be to not authorize the ROW.
After careful consideration of many factors, including the need to provide electricity to the Western United States and strengthening and stabilizing the economies of White Pine, Nye, Lincoln, and Clark Counties, and balancing those factors with the need to protect air, visual and biological resources, the BLM has selected the agency preferred alternative. The BLM's preferred alternative will approve all of the facilities described in the Proposed Action, including the transmission-line route, except the R-SS-Site B sub-alternative, including the access road and Falcon-Gondor loop-ins will replace the Robinson Summit Substation components. Various site-specific applicant-committed mitigation measures will be implemented at the development stage to protect other resources and uses.
Comments on the ON Line Draft Supplemental EIS received from the public, cooperating agencies and internal BLM reviewers were incorporated into the Final EIS. The comments resulted in corrections, clarifying text, and the addition of new text used in the analysis of impacts. The ON Line Final EIS addresses impacts of the power line on private lands and those administered by the BLM.
This decision is subject to appeal to the Interior Board of Land Appeals (IBLA) as provided in 43 CFR part 4, within 30 days from the date of publication of this Notice of Availability in the
Federal Register
. The ROD contains instructions for filing an appeal with the IBLA.
The ROD for this project addresses only BLM's decisions for public lands and resources administered by BLM.