The Commission has received two preliminary permit applications deemed filed on August 6, 2010, at 8:30 a.m.,[]
for proposed projects to be located on the Ouachita River, in Caldwell Parish, Louisiana. The applications were filed by FFP Missouri 17, LLC for Project No. 13824-000 and BOST2 Hydroelectric, LLC for Project No. 13826-000.
On February 22, 2012, at 9 a.m. (Eastern Time), the Secretary of the Commission, or her designee, will conduct a random drawing to determine the filing priority of the applicants identified in this notice. The Commission will select among competing permit applications as provided in section 4.37 of its regulations.[]
The priority established by this drawing will be used to determine which applicant, among those with identical filing times, will be considered to have the first-filed application.
The drawing is open to the public and will be held in room 2C, the Commission Meeting Room, located at 888 First Street NE., Washington, DC 20426. A subsequent notice will be issued by the Secretary announcing the results of the drawing.
Dated: February 10, 2012.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2012-3633 Filed 2-15-12; 8:45 am]
BILLING CODE 6717-01-P