This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This notice initiates the public scoping process for the EIS. Comments on issues may be submitted in writing until March 6, 2013. The date(s) and location(s) of any scoping meetings will be announced at least 15 days in advance through local media, newspapers, and the BLM Web site at: http://www.blm.gov/nv/st/en/fo/battle_mountain_ field.html. In order to be considered during the preparation of the Draft EIS, all comments must be received prior to the close of the 30 day scoping period or 15 days after the last public meeting, whichever is later. The BLM will provide additional opportunities for public participation upon publication of the Draft EIS.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Classification and Segregation for Conveyance for Recreation and Public Purposes for a Sewage Treatment Facility; Partial Termination of Recreation and Public Purposes Classification of Public Lands in Storey County, NV
Classification for Lease and Subsequent Conveyance for Recreation and Public Purposes of Public Lands (N-83501) for a High School in Sandy Valley, Clark County, NV
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
202
as of
07/19/2026 at 12:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2013-02361 as it appeared on Public Inspection on
02/01/2013 at 8:45 am.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2013-02361 (78 FR 7808)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Bureau of Land Management, Interior.
ACTION:
Notice of intent.
SUMMARY:
In compliance with the National Environmental Policy Act of 1969, as amended (NEPA), and the Federal Land Policy and Management Act of 1976, as amended, the Bureau of Land Management (BLM) Mount Lewis Field Office, Battle Mountain, Nevada, intends to prepare an Environmental Impact Statement (EIS) to analyze and disclose impacts associated with the Buffalo Valley Mine Project, a proposed open pit gold mine, mill, and associated facilities, located on public and private lands in Lander and Humboldt counties, Nevada, and by this notice is announcing the beginning of the scoping process to solicit public comments and identify issues.
DATES:
This notice initiates the public scoping process for the EIS. Comments on issues may be submitted in writing until March 6, 2013. The date(s) and location(s) of any scoping meetings will be announced at least 15 days in advance through local media, newspapers, and the BLM Web site at:
http://www.blm.gov/nv/st/en/fo/battle_mountain_field.html. In order to be considered during the preparation of the Draft EIS, all comments must be received prior to the close of the 30 day scoping period or 15 days after the last public meeting, whichever is later. The BLM will provide additional opportunities for public participation upon publication of the Draft EIS.
ADDRESSES:
You may submit comments related to the proposed Buffalo Valley Mine Project by any of the following methods:
Mail:
BLM, Mount Lewis Field Office, 50 Bastian Road, Battle Mountain, NV 89820.
Documents pertinent to this proposal may be examined at the Mount Lewis Field Office.
FOR FURTHER INFORMATION CONTACT:
For further information and/or to have your name added to our mailing list, contact Andrea Dolbear, Environmental Protection Specialist, telephone 775-635-4017; address,50 Bastian Road, Battle Mountain, NV 89820; email
asdolbear@blm.gov.
Persons who use a telecommunications device for the deaf (TDD) may call the Federal Information Relay Service (FIRS) at 1-800-877-8339 to contact the above individual during normal business hours. The FIRS is available 24 hours a day, 7 days a week, to leave a message or question with the above individual. You will receive a reply during normal business hours.
SUPPLEMENTARY INFORMATION:
Newmont Mining Corporation, in a joint venture with Fairmile Gold, proposes to construct, operate, reclaim, and close an open pit, heap leach, precious-metal, mining operation known as the Buffalo Valley Mine Project. The proposed project would be located 20 miles southwest of Battle Mountain, Nevada, and 12 miles northwest of Newmont's Phoenix Mine in Lander and Humboldt counties. The legal land description for the proposed project area is:
Mount Diablo Meridian
T. 31 N., R. 42 E.,
Secs 3, 4, 5, and 6;
T. 32 N., R. 42 E.,
Secs 27, 28, 29, 30, 31, 32, 33, and 34.
The area described contains 5,968 acres, more or less, in Lander and Humboldt counties, Nevada.
The proposed project area would be comprised of approximately 5,968 acres, of which 3,662 acres are public land administered by the BLM. Approximately 2,274 of the 3,662 acres are in Lander County and managed by the BLM Mount Lewis Field Office and approximately 1,388 acres are in Humboldt County and managed by the BLM Winnemucca District, Humboldt River Field Office. The Battle Mountain District, Mount Lewis Field Office will manage all of the public lands on this proposed project. Approximately 2,306 acres within the proposed project area are private land controlled by Newmont.
The Buffalo Valley Mine Project is in conformance with the 1986 Shoshone-Eureka Resource Area Resource Management Plan (RMP) and Record of Decision (ROD). The ROD states that all public land in the planning areas will be open for mining and prospecting unless withdrawn or restricted from mineral entry. One of the objectives of the RMP is to make available and encourage development of mineral resources to meet the national, regional, and local needs consistent with national objectives, for an adequate supply of minerals. The proposed project also conforms to the BLM Winnemucca District, 1982 Sonoma-Gerlach Management Framework Plan at Section .42 Minerals, Objective M1 to make all public lands and other federally owned minerals available for the exploration and development of mineral and material commodities.
The proposed project is estimated to produce approximately 40 million tons of ore grade material from an estimated 226 million tons of material to be extracted using conventional open pit mining methods of drilling and blasting. The proposed project would consist of the following components: 2 open pits; mine dewatering system; 3 waste rock storage areas; crushing system; heap leach pad; process facility; high-grade ore stockpile; process ponds; borrow pit; storm water pond and diversion ditches; small shop/office and maintenance facility; fuel facility; access and haul roads; top soil (growth media) stockpiles; powerline; water supply well; and exploration.
The Buffalo Valley Mine Road is a county road located in both Lander and Humboldt counties on the east side of Buffalo Valley. It bisects the proposed project area and would be rerouted to the west around the proposed project facilities. The plan of operation is to haul ore for crushing and leaching with a dilute cyanide solution. The life of the mine would be approximately 10 years. Newmont anticipates a workforce of 120 employees during the production phase of the mine.
An interdisciplinary approach will be used to develop the EIS in order to consider the variety of resource issues and concerns identified during the scoping period. Potential direct, indirect, residual, and cumulative impacts from the proposed action will be analyzed in the EIS.
The purpose of the public scoping process is to determine relevant issues that will influence the scope of the environmental analysis, including potential alternatives, and the extent to
( printed page 7809)
which those issues and impacts will be analyzed in the EIS. At present, the BLM has identified the following preliminary issues: pit lake formation post closure, mine dewatering, wildlife, and socioeconomic concerns.
The BLM will follow the NEPA public participation requirements to satisfy the public involvement requirements under Section 106 of the National Historic Preservation Act (NHPA) (16 U.S.C. 470(f)) pursuant to 36 CFR 800.2(d)(3). Any information about historic and cultural resources within the area potentially affected by the proposed project will assist the BLM in identifying and evaluating impacts to such resources in the context of both NEPA and Section 106 of the NHPA.
The BLM will consult with Indian tribes on a government-to-government basis in accordance with Executive Order 13175 and other policies. Tribal concerns, including impacts on Indian trust assets and potential impacts to cultural resources, will be given due consideration. Federal, State, and local agencies, along with tribes and other stakeholders that may be interested in or affected by the proposed Buffalo Valley Mine Project are invited to participate in the scoping process and, if eligible, may request or be requested by the BLM to participate in the development of the environmental analysis as a cooperating agency.
Before including your address, phone number, email address, or other personal identifying information in your comment, you should be aware that your entire comment—including your personal identifying information—may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information from public review, we cannot guarantee that we will be able to do so.