This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
1,929
as of
09/09/2026 at 8:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2015-11029 as it appeared on Public Inspection on
05/06/2015 at 8:45 am.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2015-11029 (80 FR 26424)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).
ACTION:
Final rule.
SUMMARY:
DoD, GSA, and NASA are issuing a final rule amending the Federal Acquisition Regulation (FAR) to implement section 802 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2013. This section provides additional requirements relative to the review and justification of pass-through contracts.
DATES:
Effective:
June 8, 2015.
FOR FURTHER INFORMATION CONTACT:
Ms. Kathy J. Hopkins, Procurement Analyst, at 202-969-7226 for clarification of content. For information pertaining to status or publication schedules, contact the Regulatory Secretariat Division at 202-501-4755. Please cite FAC 2005-82, FAR Case 2013-012.
SUPPLEMENTARY INFORMATION:
I. Background
DoD, GSA, and NASA published a proposed rule in the
Federal Register
at 79 FR 39361 on July 10, 2014 to implement section 802 of the NDAA for FY 2013 (Pub. L. 112-239) which provided for additional requirements relative to the review and justification of pass-through contracts. Specifically, in those instances where an offeror for a contract, task order, or delivery order informs the agency pursuant to FAR 52.215-22 of its intention to award subcontracts for more than 70 percent of the total cost of work to be performed under the contract, task order, or delivery order, section 802 requires the contracting officer to (1) consider the availability of alternative contract vehicles and the feasibility of contracting directly with a subcontractor or subcontractors that will perform the bulk of the work; (2) make a written determination that the contracting approach selected is in the best interest of the Government; and (3) document the basis for such determination. These statutory requirements are being implemented in FAR 15.404-1(h). For consistency, this rule is applicable to all of the agencies subject to the FAR, even though section 802 only applied to the Department of Defense, the Department of State, and the United States Agency for International Development. Contract actions under section 46 of the Small Business Act (15 U.S.C. 657s) are exempt from the requirements under section 802 of the NDAA for FY 2013.
Two respondents submitted comments on the proposed rule.
II. Discussion and Analysis
The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (the Councils) reviewed the comments in the development of the final rule. A discussion of the comments and the changes made to the rule as a result of those comments are provided as follows:
A. Summary of Significant Changes
This final rule makes two changes from the proposed rule. The first change revises FAR 15.404-1(h)(2) to make clear that competition requirements still apply if the contracting officer selects alternative approaches. The second change revises FAR 15.404-1(h)(3) to clarify that the requirements of this rule do not apply to small business set-aside contracts.
B. Analysis of Public Comments
The Regulatory Secretariat Division received responses from two respondents to the proposed rule which are discussed below:
1. Application of Rule to FAR Part 36
Comment:
One respondent requested that the final rule ensure that this new requirement take into consideration the requirements found in FAR 36.501, which addresses performance of work by prime construction contractors.
Response:
The statute does not exempt the contracting officer from making a written determination that the contracting approach selected is in the best interest of the Government under FAR part 36 acquisitions. The contracting officer shall take into consideration industry practices in making this determination.
2. Conflict With FAR 52.219-14
Comment:
One respondent stated that FAR clause 52.219-14, Limitations on Subcontracting, could also conflict with the new requirements of this rule.
( printed page 26425)
Response:
FAR clause 52.219-14, Limitations on Subcontracting, applies only to contracts that have been set aside for small business concerns or 8(a) concerns. Section 1615 of the NDAA for FY 2014 (Pub. L. 113-66) exempts contract actions subject to Section 46 of the Small Business Act (15 U.S.C. 657s). The text at FAR 15.404-1(h)(3) has been revised to clarify that contract actions awarded pursuant to FAR subparts 19.5, 19.8, 19.13, 19.14, or 19.15 are exempt from the requirements of this rule. Therefore, the requirements of this rule do not conflict with FAR clause 52.219-14.
3. Potential Increase in Bid Protests
Comment:
One respondent stated that by requiring contracting officers to consider direct award to a subcontractor that will perform more than 70 percent of the work, those subcontractors could become interested parties for bid protest purposes. This could open the door to a substantial number of bid protests and significantly impact the ability of agencies to make timely awards.
Response:
The statute requires that the contracting officer consider the availability of alternative contract vehicles and the feasibility of contracting directly with a subcontractor or subcontractors that will perform the bulk of the work, make a determination that the contracting approach selected is in the best interest of the Government, and document the basis for such determination. By following these requirements and adhering to the established solicitation procedures in the FAR, contracting officers will mitigate the risk of protests. This rule does not change existing competition requirements, nor does it change the status of subcontractors in the bid protest process.
4. Subcontractors Lacking Prime Contractor Experience
Comment:
One respondent stated that direct award to subcontractors that do not have sufficient prime experience can severely impact procurements and result in a substantial increase in workload for both the contractor and the Government (
i.e.
additional audits and business system reviews).
Response:
The statute requires that contracting officers consider direct award to subcontractors and the purpose of this rule is to amend the FAR to implement that requirement. However, it should be noted that both the statute and the rule only require that the contracting officer consider direct award. Contracting officers shall continue to ensure that purchases shall be made from, and contracts shall be awarded to, responsible prospective contractors only, in accordance with FAR 9.103.
5. Subcontractors Contracting Directly With the Government
Comment:
One respondent opined that prime contractors will try to avoid the impact of this rule by using contract provisions that prohibit subcontractors from entering into a direct contract with the agency. So, if this rule is going to work, a clause preventing primes from including a restrictive provision in a teaming arrangement and/or subcontract needs to be included in the rule.
Response:
FAR clause 52.203-6 “Restrictions on Subcontractor Sales to the Government” precludes prime contractors from including such restrictions in their agreements with actual or prospective subcontractors. For acquisitions of commercial items, the prohibition applies only to the extent that any agreement restricting sales by subcontractors results in the Federal Government being treated differently from any other prospective purchaser for the sale of the commercial item(s).
6. Subcontractor Pricing and Participation in Negotiations
Comment:
One respondent stated that in many cases, the prime contractors do not allow subcontractors to see the final version of the prime's proposal sent in response to the Government's RFP or allow subcontractors to participate in negotiations. As such, the subcontractor pricing that the Government sees in the prime contractor's proposal or during negotiations may not be accurate. This issue can be resolved by revising the proposed clause in the rule to require the prime contractor to obtain the signed approval of the subcontractor's portion of the final offer submitted to the Government and allowing subcontractors that will perform 70 percent or more work to participate in negotiations.
Response:
FAR 15.404-3 already provides requirements for evaluating subcontractor pricing and obtaining certified cost or pricing data as required. Prime contractors are responsible for managing their subcontractors and appropriately evaluating subcontractor cost or pricing data in accordance with FAR subpart 15.4.
III. Executive Orders 12866 and 13563
Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under Section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
IV. Regulatory Flexibility Act
The Department of Defense, the General Services Administration, and the National Aeronautics and Space Administration certify that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601,
et seq.,
because the rule augments the current responsibilities of contracting officers relative to the review and justification of pass-through contracts and does not initiate or impose any new administrative or performance requirements on contractors. In addition, contract actions awarded pursuant to FAR subparts 19.5, 19.8, 19.13, 19.14, or 19.15 are exempt from the requirements of this rule.
V. Paperwork Reduction Act
The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).
(h)
Review and justification of pass-through contracts.
(1) The requirements of this paragraph (h) are applicable to all agencies. The requirements apply by law to the Department of Defense, the Department of State, and the United States Agency for International Development, per section 802 of the National Defense Authorization Act (NDAA) for Fiscal Year 2013. The requirements apply as a matter of policy to other Federal agencies.
(2) Except as provided in paragraph (h)(3) of this section, when an offeror for a contract or a task or delivery order informs the contracting officer pursuant to 52.215-22 that it intends to award subcontracts for more than 70 percent of the total cost of work to be performed under the contract, task or delivery order, the contracting officer shall—
(i) Consider the availability of alternative contract vehicles and the feasibility of contracting directly with a subcontractor or subcontractors that will perform the bulk of the work. If such alternative approaches are selected, any resulting solicitations shall be issued in accordance with the competition requirements under FAR part 6;
(ii) Make a written determination that the contracting approach selected is in the best interest of the Government; and
(iii) Document the basis for such determination.
(3) Contract actions awarded pursuant to subparts 19.5, 19.8, 19.13, 19.14, or 19.15 are exempt from the requirements of this paragraph (h) (see section 1615 of the National Defense Authorization Act for Fiscal Year 2014 (Pub. L. 113-66)).