This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
There is no table of contents available for this document.
Related Documents
Enhanced Content - Related Documents
FederalRegister.gov uses the agency dockets published with the document to display related documents.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
432
as of
10/05/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2022-16120 as it appeared on Public Inspection on
07/26/2022 at 8:45 am.
It was viewed
4
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2022-16120 (87 FR 45095)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
Take notice that on July 15, 2022, Delfin LNG LLC (Delfin) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time (2022 Extension of Time Request), until September 28, 2023, to construct and place into service the facilities that were authorized in the original certificate authorization issued on September 28, 2017 (Certificate Order).[1]
The Certificate Order authorized certain “onshore facilities” that would be used exclusively to transport natural gas to Delfin's deepwater port “offshore facilities” (collectively, the Project) in federal waters offshore Louisiana. The onshore facilities would be used to meet the requirements of the customers of the offshore facilities. The Commission subsequently has granted three, successive one-year extensions of this in-service timing condition, with the result that the facilities currently are required to be made available for service by September 28, 2022.[2]
In its 2022 Extension of Time Request, Delfin states that it has made significant progress in developing the Project. Delfin asserts that the market for LNG is strong with the current geopolitical importance of the Ukraine invasion and the initiative of the European Union to increase deliveries of U.S LNG to Europe. Additionally, Delfin states that the Project remains commercially viable with a binding LNG sale and purchase agreement with Vitol Spa for 0.5 million metric tonnes per annum (mtpa) of LNG delivered free on-board at the Delfin LNG deepwater port, for 15 years. Moreover, Delphin explains that it has continued to work to develop the Project by completing the Front End Engineering and Design for the construction of the Floating LNG vessels (FLNGV). Delfin states the project consists of 4 separates floating FLNGV, and only requires 2.0 to 2.5 mtpa of LNG for the long-term off-take contracts to support a final investment (FID) and begin construction of the first FLNGV. Moreover, Delfin affirms that FID for the first FLNGV is on schedule for the end of the year. Accordingly, Delfin requests an extension of time until September 28, 2023 to complete construction of the onshore facilities and place them into service.
This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on Delfin's request for an extension of time may do so. No reply
( printed page 45096)
comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).
As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,[3]
the Commission will aim to issue an order acting on the request within 45 days.[4]
The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[5]
The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act.[6]
At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.[7]
The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested.
In addition to publishing the full text of this document in the
Federal Register
, The Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (
http://www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID-19), issued by the President on March 13, 2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov
or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.
The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFiling” link at
http://www.ferc.gov.
Persons unable to file electronically should submit an original and three copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.
Comment Date:
5:00 p.m. Eastern Time on, August 5, 2022.
6.
Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission's environmental analysis for the permit order complied with NEPA.