This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Kaukauna Utilities; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
There is no table of contents available for this document.
Related Documents
Enhanced Content - Related Documents
FederalRegister.gov uses the agency dockets published with the document to display related documents.
Kaukauna Utilities; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments
Public Comments
Enhanced Content - Public Comments
This feature is not available for this document.
Regulations.gov Data
Enhanced Content - Regulations.gov Data
Additional information is not currently available for this document.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
65
as of
07/18/2026 at 10:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2022-16713 as it appeared on Public Inspection on
08/03/2022 at 8:45 am.
It was viewed
4
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2022-16713 (87 FR 47738)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.
a.
Type of Application:
New Major License.
b.
Project No.:
2715-026.
c
. Date filed:
July 22, 2022.
d.
Applicant:
Kaukauna Utilities.
e.
Name of Project:
Combined Locks Hydroelectric Project (Combined Locks Project).
f.
Location:
On the Lower Fox River in the Village of Combined Locks and the Village of Little Chute, Outagamie County, Wisconsin. The project does not include any federal land.
j.
Cooperating agencies:
Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission's policy that agencies that cooperate in the preparation of the environmental document cannot also intervene.
See,
94 FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant.
l. Deadline for filing additional study requests and requests for cooperating agency status: September 20, 2022.
The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission's eFiling system at
http://www.ferc.gov/docs-filing/efiling.asp.
For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov,
(866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P-2715-026.
m. The application is not ready for environmental analysis at this time.
n.
The Combined Locks Project consists of:
(1) a concrete and cyclopean stone dam approximately 654 feet long and 27 feet high with additional 24 inch nominal flashboards mounted upon the
( printed page 47739)
spillway crest at elevation 674.6 feet International Great Lakes Datum of 1985 (IGLD85); (2) a 126.9-acre reservoir at normal full pool elevation 676.7 feet IGLD85; (3) a powerhouse approximately 65 feet wide by 130 feet long housing two 3.1-megawatt (MW) generators, for a total authorized capacity of 6.2 MW; (4) a tailrace channel; (5) a 265-foot-long, 4.16-kilovolt (kV) interconnection line from the powerhouse to transformer and 1,442-foot-long, 12.47-kV interconnection line from the transformer to the substation; and (6) appurtenant facilities.
o. A copy of the application may be viewed on the Commission's website at
http://www.ferc.gov
using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID-19), issued by the President on March 13, 2020. For assistance, contact FERC Online Support.
You may also register online at
http://www.ferc.gov/docs-filing/esubscription.asp
to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
p.
Procedural schedule and final amendments:
The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate.
Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.
Issue Deficiency Letter (if necessary)—September 2022
Request Additional Information (if necessary)—September 2022
Issue Scoping Document 1 for comments—March 2023
Issue Scoping Document 2 (if necessary)—July 2023
Issue Notice of Ready for Environmental Analysis—July 2023