This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Comments on the collection of information are due June 15, 2023.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
63
as of
06/08/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2023-10351 as it appeared on Public Inspection on
05/15/2023 at 8:45 am.
It was viewed
4
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2023-10351 (88 FR 31258)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Federal Energy Regulatory Commission, Department of Energy.
ACTION:
Notice of information collection and request for comments.
SUMMARY:
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on a new information collection, FERC-725D(1), Mandatory Reliability Standards FAC-001-4 and FAC-002-4. This notice will be part of an information collection request that will be submitted to the Office of Management and Budget (OMB) for a review of the information collection requirements.
DATES:
Comments on the collection of information are due June 15, 2023.
ADDRESSES:
Send written comments on FERC-725D(1) to OMB through
www.reginfo.gov/public/do/PRAMain,
Attention: Federal Energy Regulatory Commission Desk Officer. Please identify the OMB control number (1902-NEW) in the subject line. Your comments should be sent within 30 days of publication of this notice in the
Federal Register
.
Please submit copies of your comments (identified by Docket No. RD22-5-000) to the Commission as noted below. Electronic filing through
https://www.ferc.gov
is preferred.
Electronic Filing:
Documents must be filed in acceptable native applications and print-to-PDF, but not in scanned or picture format.
For those unable to file electronically, comments may be filed by USPS mail or by hand (including courier) delivery.
( printed page 31259)
○
Mail via U.S. Postal Service Only:
Addressed to: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street NE, Washington, DC 20426.
○
Hand (including courier) delivery: Deliver to:
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852.
Instructions:
OMB submissions
must be formatted and filed in accordance with submission guidelines at
www.reginfo.gov/public/do/PRAMain; Using the search function under the “Currently Under Review field,” select Federal Energy Regulatory Commission; click “submit” and select “comment” to the right of the subject collection.
FERC submissions must be formatted and filed in accordance with submission guidelines at:
https://www.ferc.gov.
For user assistance, contact FERC Online Support by email at
ferconlinesupport@ferc.gov,
or by phone at: (866) 208-3676 (toll-free).
Docket:
Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at
https://www.ferc.gov.
FOR FURTHER INFORMATION CONTACT:
Ellen Brown may be reached by email at
DataClearance@FERC.gov
and telephone at (202) 502-8663.
SUPPLEMENTARY INFORMATION:
Title:
FERC-725D(1), RD22-5-000, Mandatory Reliability Standards FAC-001-4 and FAC-002-4.
OMB Control No.:
1902-NEW.
Respondents:
Transmission owners and generator owners for Reliability Standard FAC-001-4. Planning coordinators for Reliability Standard FAC-002-4.[1]
Frequency of Information Collection:
Once during years 1 and 2. On occasion during year 3 and beyond.
Abstract:
The Facilities Design, Connections, and Maintenance Reliability Standards address topics such as facility interconnection requirements, facility ratings, system operating limits, and transfer capabilities. These Reliability Standards are designated with the prefix “FAC.”
On November 23, 2002 the Commission published an order approving new Reliability Standards FAC-001-4 and FAC-002-4 (87 FR 71602). The Commission approved those new standards to help ensure appropriate coordination and communication regarding the interconnection of facilities.
At present, the collections of information associated with all “FAC” Reliability Standards are authorized under FERC-725D (OMB Control Number 1902-0247). Ordinarily, the Commission would ask OMB to approve the collections of information associated with the new Reliability Standards as revisions of FERC-725D. However, another information collection request pertaining to FERC-725D is pending at OMB,[2]
and only one request per information collection is allowed to be pending at OMB at the same time. FERC-725D(1) is a temporary placeholder number to avoid conflicting with the pending request already submitted to OMB regarding FERC-725D.
Previous Reliability Standard FAC-001-003 required transmission owners and generator owners to complete coordinated studies on new or “materially modified” existing interconnections. As approved in the November 23, 2022 order, FAC-001-4 requires coordinated studies of “qualified changes” in interconnections instead of “materially modified” interconnections. This revision is intended to prevent confusion with the Commission-defined term “Material Modification” in
pro forma
interconnection procedures and agreements.[3]
The term “qualified changes” refers to changes in existing interconnected facilities that can have reliability impacts and helps ensure that they are properly addressed in interconnection requirements and studies.
In the November 23 order, the Commission also revised Requirement R6 of existing Reliability Standard FAC-002-3 by authorizing the planning coordinator to define the term “qualified change” and requiring public posting of the definition.
Necessity of Information:
Mandatory.
Internal Review:
The Commission has reviewed the collections of information associated with the rulemaking in Docket No. RD22-5-000, and has determined that the described information collection activities are necessary. These requirements conform to the Commission's need for efficient information collection, communication, and management within the energy industry.
Estimate of Annual Burden:
The responsibilities of applicable entities for FAC-001-4 (
i.e.,
transmission owners and generator owners) are the same as those approved for Reliability Standard FAC-001-3 in FERC-725D. Table 1, below, accordingly shows the same burdens as approved in FERC-725D, with updated costs.
Table 1—Estimated Burdens for FAC-001-4
Types of responses
Types and
numbers of
respondents
Number of
annual
responses per
respondent
Total
number of
responses
Average
number of
burden hours
and cost per response 4
Total burden
hours
and cost
A
B
C
D (Column B × Column C)
E
F (Column D × Column E)
Documentation & Updates
498 GOs/TOs
1
498
34 hrs.; $3,094
16,932 hrs. $1,491,672.
Evidence Retention
498 GOs/TOs
1
498
1 hr.; $91.00
498 hrs.; $45,318.
( printed page 31260)
Under, FAC-002-4, the new collection FERC-725D(1) represents a minor additional burden to planning coordinators, due to the requirement that they develop the definition of “qualified change” for new and existing interconnections of generation, transmission or electricity end user facilities. This burden is expected to be greater in years one and two than in year three and beyond for FAC-002-4. The burden and cost estimates for FAC-002-4 are based on the increase in the reporting and recordkeeping burden imposed by the revised Reliability Standards. Our estimates are based on the NERC Compliance Registry as of September 16, 2022, which indicates 63 planning coordinators.
Table 2—Estimated Burdens for FAC-002-4
Type and numbers of respondents
Number of
annual
responses per
respondent
Total
number of
responses
Average
number of
burden hours
and cost per response
Total burden
hours
and cost
A
B
C (Column A × Column B)
D
E (Column C × Column D)
63 PA/PCs Years 1 and 2
1
63
120 hrs.; $7,200
7,560 hrs.; $453,600.
63 PA/PCs Ongoing, beginning in Year 3
1
63
40 hrs.; $2,520
2,520 hrs.; $158,760.
Comments are invited on:
(1) whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency's estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology.
Dated: May 9, 2023.
Kimberly D. Bose,
Secretary.
Footnotes
1.
The NERC Glossary, at
https://www.nerc.com/pa/Stand/Glossary%20of%20Terms/Glossary_of_Terms.pdf,
defines these terms. A transmission owner (TO) is the entity that owns and maintains transmission facilities. A generator owner (GO) is the entity that owns and maintains generating units. A planning coordinator, formerly known as a planning authority (PA/PC), is the responsible entity that coordinates and integrates transmission facilities, service plans, resource plans, and protection systems.
2.
That pending request would not affect FAC-001-3 or FAC-002-3, the predecessors to the Reliability Standards approved by the Commission in its November 23, 2022 order.
3.
The regulation at 18 CFR 35.28(c)(1) requires every public utility that owns, controls, or operates facilities used for the transmission of electric energy in interstate commerce to have on file with the Commission an open access transmission tariff consisting of the
pro forma
tariff promulgated by the Commission, or such other tariff as may be approved by the Commission. The regulation at 18 CFR 35.28(f)(1) requires every public utility that is required to have on file a non-discriminatory open access transmission tariff to amend such tariff by adding the standard interconnection procedures and agreement and the standard small generator interconnection procedures and agreement required by the Commission.
4.
The Commission staff estimates that the industry's hourly cost for wages plus benefits is similar to the Commission's $91.00 FY 2022 average hourly cost for wages and benefits.