This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
There is no table of contents available for this document.
Related Documents
Enhanced Content - Related Documents
FederalRegister.gov uses the agency dockets published with the document to display related documents.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
88
as of
11/07/2026 at 12:15 am EST
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2023-14991 as it appeared on Public Inspection on
07/13/2023 at 8:45 am.
It was viewed
1
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2023-14991 (88 FR 45199)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
This notice revises the Federal Energy Regulatory Commission's (Commission) schedule for processing Black Canyon Hydro, LLC's license application for the
( printed page 45200)
Seminoe Pumped Storage Project. A prior notice issued on March 31, 2023, identified an anticipated schedule for issuance of draft and final National Environmental Policy Act (NEPA) documents and a final order for the project. After the issuance of that notice, Black Canyon Hydro, LLC agreed to conduct additional studies requested by the agencies and file the study results by “November 2023,” and Commission staff issued a letter requiring the corresponding study reports and additional information to be filed with the Commission by November 30, 2023. To account for the additional time needed for Black Canyon Hydro, LLC to complete the studies and file the additional information, the application will be processed according to the following revised schedule.
Notice of Ready for Environmental Analysis:
February 2024
Draft NEPA Document:
October 2024
Final NEPA Document:
May 9, 2025
In addition, in accordance with Title 41 of the Fixing America's Surface Transportation Act, enacted on December 4, 2015, agencies are to publish completion dates for all federal environmental reviews and authorizations. This notice identifies the Commission's anticipated schedule for issuance of the final order for the project, which is based on the revised issuance date for the final NEPA document. Accordingly, we currently anticipate issuing a final order for the project no later than:
Issuance of Final Order:
September 18, 2025
If a schedule change becomes necessary, an additional notice will be provided so that interested parties and government agencies are kept informed of the project's progress.