This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Rescission and Termination of the Environmental Impact Statement Analyzing the Potential Environmental Effects From Maintaining Secretary Jewell's Coal Leasing Moratorium
This rescission and termination takes effect immediately.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Rescission and Termination of the Environmental Impact Statement Analyzing the Potential Environmental Effects From Maintaining Secretary Jewell's Coal Leasing Moratorium
Rescission and Termination of the Environmental Impact Statement Analyzing the Potential Environmental Effects From Maintaining Secretary Jewell's Coal Leasing Moratorium
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
533
as of
09/16/2026 at 2:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2025-06388 as it appeared on Public Inspection on
04/14/2025 at 8:45 am.
It was viewed
32
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2025-06388 (90 FR 15719)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Bureau of Land Management, Interior.
ACTION:
Notice of rescission and termination.
SUMMARY:
The Bureau of Land Management (BLM), Headquarters Solid Minerals is announcing the rescission of the Notice of Intent to prepare an environmental impact statement (EIS) and termination of the EIS analyzing the potential environmental effects from maintaining Secretary Jewell's coal leasing moratorium.
DATES:
This rescission and termination takes effect immediately.
FOR FURTHER INFORMATION CONTACT:
Indra Dahal, Solid Minerals Deputy Division Chief, at 571-458-6637, or by email to
idahal@blm.gov.
Individuals in the United States who are deaf, deafblind, hard of hearing, or have a speech disability may dial 711 (TTY, TDD, or TeleBraille) to access telecommunications relay services. Individuals outside the United States should use the relay services offered within their country to make international calls to the point-of-contact in the United States.
SUPPLEMENTARY INFORMATION:
Pursuant to the National Environmental Policy Act of 1969 (NEPA), the BLM published on May 1, 2023, its Notice of Intent (NOI) to prepare an EIS to analyze the potential environmental effects from maintaining Secretary Jewell's coal leasing moratorium (88 FR 26588). The EIS would have analyzed the potential effects from maintaining or revoking former Secretary of the Interior Sally Jewell's coal leasing moratorium.
Background Information:
In January 2016, then-Secretary of the Interior Sally Jewell issued Secretary's Order 3338 (Jewell Order) commencing preparation of a new programmatic EIS and establishing a moratorium on Federal coal leasing, with some exemptions.
On March 29, 2017, then-Secretary of the Interior Ryan Zinke implemented Executive Order (E.O.) 13783, “Promoting Energy Independence and Economic Security,” by issuing Secretary's Order 3348 (Zinke Order), which rescinded the Jewell Order and ended the moratorium on coal leasing. Immediately thereafter, Citizens for Clean Energy, Ecocheyenne, Montana Environmental Information Center, Center for Biological Diversity, Defenders of Wildlife, Sierra Club, WildEarth Guardians, and the Northern Cheyenne Tribe filed a lawsuit in the U.S. District Court for the District of Montana asserting that the issuance of the Zinke Order required an environmental analysis in compliance with NEPA. Additionally, the States of California, New York, New Mexico, and Washington also filed suit and the Court consolidated the cases. The National Mining Association and the States of Wyoming and Montana intervened.
On April 19, 2019, the Court held that the Zinke Order was a final agency action that triggered the need to comply with NEPA, requiring the Department to conduct an appropriate environmental review of that action. To comply with the Court's Order, the BLM released an environmental assessment (EA) for public comment on May 22, 2019, and published the final EA and a Finding of No Significant Impact (FONSI) on its website on February 26, 2020. Shortly thereafter, the Plaintiffs amended their complaints to challenge the scope and content of the EA.
On January 20, 2021, President Biden issued E.O. 13990, entitled, “Executive Order on Protecting Public Health and the Environment and Restoring Science to Tackle the Climate Crisis,” revoking
( printed page 15720)
E.O. 13783. On April 16, 2021, Secretary Haaland rescinded the Zinke Order through Secretary's Order 3398 (Haaland Order) but did not reinstate the Federal coal leasing moratorium.
On August 12, 2022, the Court vacated and remanded the EA and associated FONSI and reinstated “[t]he coal leasing program moratorium established by the Jewell Order until the completion of sufficient NEPA review analyzing revocation of the moratorium.” That court ruling was the impetus for publishing the BLM's NOI to prepare an EIS to analyze the potential environmental effects from maintaining Secretary Jewell's coal leasing moratorium on May 1, 2023 (88 FR 26588).
In October 2022, Intervenor-Defendants appealed the decision to the U.S. Court of Appeals for the Ninth Circuit. On February 21, 2024, the Ninth Circuit ruled that the District Court's ruling was incorrect, that the Haaland Order definitively revoked the Zinke Order in its entirety, and that the repeal of the Zinke Order is enough to render the case moot and appropriate for dismissal. For those reasons, the Ninth Circuit vacated and remanded the District Court decision with instructions to dismiss the case as moot. As a result, there is no Jewell Order coal leasing moratorium in effect to analyze, and the BLM is rescinding the Notice of Intent to prepare an EIS and is terminating the EIS announced in the
Federal Register
at 88 FR 26588.