This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
1,248
as of
07/11/2026 at 6:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2025-12464 as it appeared on Public Inspection on
07/01/2025 at 2:30 pm.
It was viewed
67
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2025-12464 (90 FR 29423)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Federal Energy Regulatory Commission.
ACTION:
Final rule.
SUMMARY:
The Federal Energy Regulatory Commission is issuing this final rule to revise its regulations implementing the National Environmental Policy Act and its Rules of Practice and Procedure to remove reference to the Council on Environmental Quality's rescinded regulations.
DATES:
This rule will become effective August 18, 2025.
FOR FURTHER INFORMATION CONTACT:
Thomas Blonkowski, Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-8950.
thomas.blonkowski@ferc.gov
Brandon Cherry, Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-8328,
brandon.cherry@ferc.gov
SUPPLEMENTARY INFORMATION:
I. Background
1. The Federal Energy Regulatory Commission (Commission) is issuing this final rule to remove references to the Council on Environmental Quality's (CEQ) rescinded regulations from the Commission's part 380 Regulations Implementing the National Environmental Policy Act [1]
(NEPA) and part 385 Rules of Practice and Procedure.[2]
II. Discussion
2. The Commission's regulations, since 1970, have included provisions to implement NEPA.[3]
On December 17, 1987, the Commission revised its regulations to include its part 380 regulations implementing NEPA.[4]
In the 1987 rulemaking, the Commission explained that the part 380 regulations require applicants to provide specific information on the environmental
( printed page 29424)
impacts of a proposed project under the Natural Gas Act or Federal Power Act and develop specific procedures for the Commission to evaluate project applications.[5]
The Commission also clarified that it was voluntarily complying with the CEQ regulations.[6]
3. CEQ removed its NEPA implementing regulations from the Code of Federal Regulations, 40 CFR 1500-1508, effective April 11, 2025.[7]
As CEQ explained in its rulemaking, Executive Order 14154,
Unleashing American Energy,[8]
repealed Executive Order 11991,
Relating to Protection and Enhancement of Environmental Quality,
which directed CEQ to promulgate regulations and required Federal agencies to comply with the CEQ regulations.[9]
4. The Commission's regulations include reference to CEQ's rescinded regulations at 18 CFR 380.1, 380.3, 380.4, 380.7, 380.8, 380.9, and 385.2201. As CEQ's regulations have been rescinded, this rulemaking removes those references and, where applicable, the citation to CEQ's regulation is replaced with a citation to NEPA.
III. Regulatory Planning and Review
5. Executive Order 12866,
Regulatory Planning and Review,
as amended by Executive Orders 14215,
Ensuring Accountability for All Agencies
and 13563,
Improving Regulation and Regulatory Review,
directs agencies to assess the costs and benefits of available regulatory alternatives, and if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). Executive Order 13563 emphasizes the importance of quantifying costs and benefits, reducing costs, harmonizing rules, and promoting flexibility. The Office of Information and Regulatory Affairs has designated this final rule “a significant regulatory action” as defined under section 3(f) of Executive Order 12866, though not economically significant under 3(f)(1). Accordingly, the Commission submitted this final rule to Office of Management and Budget (OMB) for Executive Order 12866 review. This final rule is considered a deregulatory action under Executive Order 14192,
Unleashing Prosperity Through Deregulation.
IV. Information Collection Statement
6. OMB regulations implementing the Paperwork Reduction Act require agencies to seek approval for information collection requirements imposed by agency rules.[10]
This final rule, however, results in no new, additional, or different reporting burdens. This final rule does not require applicants under the Federal Power Act or Natural Gas Act, or indeed any participant in a Commission proceeding, to file new, additional, or different information, and it does not change the frequency with which they must file information.
V. Environmental Analysis
7. Under NEPA, the Commission is required to prepare an Environmental Assessment or an Environmental Impact Statement for any action that may have a significant adverse effect on the human environment.[11]
Section 380.4 of the Commission's regulations sets out categorical exclusions for projects or actions that do not individually or cumulatively have a significant effect on the human environment, which negates the need to prepare an Environmental Assessment or Environmental Impact Statement.[12]
Section 380.4(a)(2)(ii) provides a categorical exclusion for the promulgation of rules that are clarifying, corrective, or procedural or that do not substantially change the effect of the regulations being amended.[13]
This rule is clarifying and corrective as it amends the Commission's regulations to remove references to CEQ's rescinded regulations. Accordingly, this rulemaking is categorically excluded from the requirement to prepare an Environmental Assessment or Environmental Impact Statement under that provision.
VI. Regulatory Flexibility Act
8. The Regulatory Flexibility Act of 1980 (RFA) [14]
generally requires a description and analysis of final rules that will have a significant economic impact on a substantial number of small entities. This final rule removes now-nugatory references to rescinded regulations, and it will not have such an impact. The Commission therefore certifies that this final rule will not have a significant economic impact on a substantial number of small entities. Accordingly, an analysis under the RFA is not required.
VII. Document Availability
9. In addition to publishing the full text of this document in the
Federal Register
, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (
http://www.ferc.gov).
10. From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.
11. User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at
ferconlinesupport@ferc.gov,
or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at
public.referenceroom@ferc.gov.
VIII. Effective Date and Congressional Notification
12. The provisions of 5 U.S.C. 801 regarding Congressional review of final rules do not apply to this final rule because the rule concerns the removal of references to CEQ's rescinded regulations and therefore is a rule of agency procedure or practice that will not substantially affect the rights or obligations of non-agency parties.[15]
13. Under 5 U.S.C. 553(b)(B), notice-and-comment rulemaking procedures are not required when the agency for good cause finds that notice and public procedure are impracticable, unnecessary, or contrary to the public interest. Notice-and-comment procedures are unnecessary for this rule because it merely clarifies and corrects the Commission's NEPA procedures by removing references to CEQ's rescinded regulations.[16]
Public comment would serve no purpose here because the Commission's action removes references to regulatory provisions that, for reasons outside of the Commission's control, have been rendered legally inoperative. In short, CEQ's recission of its own regulations provides good cause for the Commission to remove without prior
( printed page 29425)
solicitation of comment references to CEQ's regulations from the Commission's regulations, so observance of that procedure here is unnecessary.
The regulations in this part implement the Federal Energy Regulatory Commission's procedures under the National Environmental Policy Act of 1969 (NEPA).
Environmental information to be supplied by an applicant.
(a) * * *
(2) For any proposal not identified in paragraph (a)(1) of this section, any environmental information that the Commission may determine is necessary for compliance with these regulations, NEPA, and other Federal laws such as the Endangered Species Act, the National Historic Preservation Act or the Coastal Zone Management Act.
(1) The Commission and its staff will independently evaluate environmental information supplied in an application and in comments by the public. Where circumstances indicate that an action may be a major Federal action significantly affecting the quality of the human environment, the Commission:
(i) May require an environmental report or other additional environmental information, and
(ii) Will prepare an environmental assessment or an environmental impact statement.
In addition to the requirements for an environmental impact statement prescribed in section 102(2)(C) of NEPA, 42 U.S.C. 4332(2)(C), an environmental impact statement prepared by the Commission will include a section on the literature cited in the environmental impact statement and a staff conclusion section. The staff conclusion section will include summaries of:
(a) The significant environmental impacts of the proposed action;
(b) Any alternative to the proposed action that would have a less severe environmental impact or impacts and the action preferred by the staff;
(c) Any mitigation measures proposed by the applicant, as well as additional mitigation measures that might be more effective;
(d) Any significant environmental impacts of the proposed action that cannot be mitigated; and
(e) References to any pending, completed, or recommended studies that might provide baseline data or additional data on the proposed action.
The preparation of environmental documents, as defined in section 111(5) of NEPA, 42 U.S.C. 4336e(5), on hydroelectric projects, natural gas facilities, and electric transmission facilities in national interest electric transmission corridors is the responsibility of the Commission's Office of Energy Projects, 888 First Street NE, Washington, DC 20426, (202) 502-8700. Persons interested in status reports or information on environmental impact statements or other elements of the NEPA process, including the studies or other information the Commission may require on these projects, can contact this office.
(1) Any document, or a summary of the substance of any oral communication, obtained through an exempt off-the-record communication under paragraphs (e)(1)(ii), (iv), (v), (vi) or (vii) of this section, promptly will be submitted to the Secretary and placed in the decisional record of the relevant Commission proceeding, unless the communication was with a cooperating agency as described by 42 U.S.C. 4336e(2), made under paragraph (e)(1)(v) of this section.