This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Comments are no longer being accepted.
See DATES for details.
Regulations.gov Data
Enhanced Content - Regulations.gov Data
FederalRegister.gov retrieves relevant information about this document
from Regulations.gov to provide users with additional context. This
information is not part of the official Federal Register document.
Federal Registers for Applications, Notices, and Orders - Miscellaneous
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
1,110
as of
08/11/2026 at 6:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2025-14732 as it appeared on Public Inspection on
08/01/2025 at 8:45 am.
It was viewed
128
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2025-14732 (90 FR 36518)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Federal Railroad Administration, Department of Transportation.
ACTION:
Notice of rescission.
SUMMARY:
The Federal Railroad Administration (FRA) is announcing that it is rescinding its Notice of Intent (NOI) and will not prepare the Environmental Impact Statement (EIS) for the proposed Baltimore-Washington Superconducting Magnetic Levitation (SCMAGLEV) Project described therein. FRA previously issued a NOI to prepare an EIS in the
Federal Register
on November 15, 2016.
DATES:
This rescission is effective immediately.
FOR FURTHER INFORMATION CONTACT:
Please contact Marlys Osterhues, Office of Environmental Program Management, 202-774-8646, or via email at
marlys.osterhues@dot.gov.
SUPPLEMENTARY INFORMATION:
FRA awarded the Maryland Department of Transportation (MDOT) $27,800,000 through FRA's Magnetic Levitation Deployment grants program (MAGLEV Grants Program), authorized under 23 U.S.C. 322, note, for preliminary engineering and environmental review for the SCMAGLEV Project. The award was made through Cooperative Agreement No. FR-MPS-0002-16. The project would have deployed a new SCMAGLEV system between Washington, DC, and Baltimore, MD, with an intermediary stop at Baltimore/Washington International Thurgood Marshall (BWI) Airport. MDOT partnered with Baltimore Washington Rapid Rail (BWRR) to design the SCMAGLEV system. BWRR would have been responsible for construction and operation of the system. FRA, in cooperation with MDOT, initiated an EIS and published an NOI on November 15, 2016, at 81 FR 85319. FRA published a draft EIS (DEIS) for the project on January 15, 2021. Following the end of the 2021 public comment period on the DEIS, FRA paused the environmental review process on the Federal Permitting Dashboard.[1]
The purpose of the pause was to allow MDOT and BWRR additional time to agree on funding to continue the environmental review process and allow FRA and MDOT additional time to review project elements and consider next steps. Since August 24, 2021, the environmental review process has remained paused.
FRA has determined preparation of the final EIS for the SCMAGLEV Project is no longer feasible. FRA has found the current SCMAGLEV Project alternatives are likely to result in unresolvable significant effects to federal agencies, federal property, and critical agency infrastructure and operations during project construction and operation, including to the National Security Agency (NSA), U.S. Department of Defense (DOD) and Fort George G. Meade, National Aeronautics and Space Administration (NASA), U.S Department of Agriculture (USDA), U.S. Secret Service (USSS), U.S. Department of Interior (DOI)—U.S. Fish and Wildlife Service (FWS) and National Park Service (NPS), and the Department of Labor (DOL). Following extensive consultation with these agencies, FRA determined the direct effects would have substantial negative effects to agency operations or to important resources managed by federal agencies. In addition, indirect effects would also significantly impair critical infrastructure and operations and ongoing agency missions.
FRA reviewed project elements to consider whether the DEIS alternatives could be modified to address the agencies' concerns. FRA considered whether modifying the project design of the alternatives, such as locating the SCMAGLEV system entirely underground, would avoid impacts to federal agencies; however, based on agency coordination, FRA found this modification would not address the agencies' collective concerns due to the location of the tunnel and the necessity to locate required ancillary features aboveground (
e.g.,
fresh air/emergency egress [FA/EE]). In addition, BWRR had previously raised technical concerns with a completely underground system, citing cost and constructability, and advised FRA that its 180-acre trainset maintenance facility (TMF) likely could not be located underground.[2]
Similarly, FRA considered whether certain project elements (
e.g.,
TMF, FA/EE facilities) could be relocated to avoid impacts. However, BWRR has noted that the system is designed to meet the Central Japan Railway Company's (JRC's) [3]
requirements for SCMAGLEV operations and relocation of project elements like the TMF would be inconsistent with JRC's requirements.[4]
In addition, FRA also considered whether the project's Purpose and Need Statement, which was developed consistent with the statutory requirements of the MAGLEV Grants Program and BWRR's technical requirements for system safety and performance, constrained potential modifications to the DEIS alternatives. For example, the Purpose and Need Statement describes the project's objective to achieve optimal speed. Based on BWRR's ridership analysis, a speed up to 310 mph would be necessary to generate revenue to sustain the SCMAGLEV system, accounting for other factors such as power consumption, aerodynamics, and human comfort.[5]
However, achieving this top speed requires a specific geometry for the SCMAGLEV guideway, which constrains the ability to avoid sensitive resources, such as the U.S. Fish and Wildlife-managed Patuxent Wildlife Refuge. In addition, the DEIS Purpose and Need Statement was developed prior to the significant federal investment in the Northeast Corridor (NEC) from the Infrastructure Investment and Jobs Act, which is intended to improve intercity passenger rail service along with NEC. Accordingly, many of the conclusions of the Purpose and Need statement may no longer be valid.
FRA found the alternatives analyzed in the DEIS cannot be modified to avoid, minimize, and mitigate significant effects to federal agencies and federal property. On June 23, 2025, at the request of BWRR, FRA coordinated a meeting with the federal land-owning and permitted agencies, BWRR, MDOT and FRA representatives. During the meeting, BWRR presented the proposed project alignment. In response, the agencies emphasized that their previous comments and significant concerns with the project described in the draft EIS remain, further underscoring that the project is not feasible as proposed. Therefore, FRA will not prepare a final EIS.
( printed page 36519)
FRA received over 6,000 comments on the DEIS and attended three public meetings with testimony from members of the public and other stakeholders. FRA reviewed a high-level summary of the public comments prepared by MDOT. Members of the public were generally supportive of the use of SCMAGLEV technology; the development of a new transportation option; as well as potential growth and economic benefits and job creation from the project. Members of the public also raised concerns with potential effects from project construction and operation, energy consumption, and impacts to communities that would not be directly served by the SCMAGLEV Project. By rescinding the NOI, FRA is not precluding future deployment of SCMAGLEV technology in the United States.