This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
RG 1.220, Revision 0, takes effect on June 4, 2026. Post- promulgation comments must be received by July 6, 2026. Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date. Although a time limit is given, comments and suggestions in connection with items for inclusion in guides currently being developed or improvements in all published guides are encouraged at any time.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Direct final guide; issuance and post-promulgation comment period.
Regulatory Guide: Acceptability of ASME OM-2 Code, Component Testing Requirements at Nuclear Facilities
Public Comments
Enhanced Content - Public Comments
Comments are no longer being accepted.
See DATES for details.
1 comment has
been received at Regulations.gov.
Agencies review all submissions and may choose to redact, or withhold,
certain submissions (or portions thereof). Submitted comments may not be
available to be read until the agency has approved them.
Docket Title
Document ID
Comments
Acceptability of ASME OM-2 Code, Component Testing Requirements at Non-Water-Cooled Nuclear Facilities
FederalRegister.gov retrieves relevant information about this document
from Regulations.gov to provide users with additional context. This
information is not part of the official Federal Register document.
Acceptability of ASME OM-2 Code, Component Testing Requirements at Non-Water-Cooled Nuclear Facilities
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
204
as of
09/07/2026 at 2:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2026-11191 as it appeared on Public Inspection on
06/03/2026 at 8:45 am.
It was viewed
6
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2026-11191 (91 FR 33770)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Direct final guide; issuance and post-promulgation comment period.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC) is issuing Regulatory Guide (RG) 1.220, Revision 0, “Acceptability of ASME OM-2 Code, Component Testing Requirements at Nuclear Facilities.” This new RG endorses, with a regulatory position, the American Society of Mechanical Engineers (ASME) Operation and Maintenance OM-2 Code,
Component Testing Requirements at Nuclear Facilities,
2024 Edition, and describes an approach that is acceptable to the NRC staff for the development and implementation of an Inservice Testing (IST) Program for all types of nuclear facilities. This RG is effective on the date of
Federal Register
Notice publication, with a 30-day post-promulgation comment period.
DATES:
RG 1.220, Revision 0, takes effect on June 4, 2026. Post-promulgation comments must be received by July 6, 2026. Comments received after this date
( printed page 33771)
will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date. Although a time limit is given, comments and suggestions in connection with items for inclusion in guides currently being developed or improvements in all published guides are encouraged at any time.
ADDRESSES:
You may submit comments on RG 1.220, Revision 0, by any of the following methods; however, the NRC encourages electronic comment submission through the Federal rulemaking website.
Federal Rulemaking Website:
Go to
https://www.regulations.gov
and search for Docket ID NRC-2025-0677. Address questions about Docket IDs in
Regulations.gov
to Bridget Curran; telephone: 301-415-1003; email:
Bridget.Curran@nrc.gov. For technical questions, contact the individual(s) listed in the
FOR FURTHER INFORMATION CONTACT
section of this document.
Mail comments to:
Office of Administration, Mail Stop: TWFN-5-A85, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting comments, see “Obtaining Information and Submitting Comments” in the
SUPPLEMENTARY INFORMATION
section of this document.
FOR FURTHER INFORMATION CONTACT:
Thomas Scarbrough, Office of Nuclear Reactor Regulation, telephone: 301-415-2794; email:
Thomas.Scarbrough@nrc.gov
and Amir Mobasheran, Office of Nuclear Regulatory Research, telephone: 301-415-8112; email:
Amir.Mobasheran@nrc.gov. Both are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2025-0677 when contacting the NRC about the availability of information for this action. You may obtain publicly available information related to this action by any of the following methods:
NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly available documents online in the ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/adams.html. To begin the search, select “Begin ADAMS Public Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to
PDR.Resource@nrc.gov.
RG 1.220, Revision 0, “Acceptability of ASME OM-2 Code, Component Testing Requirements at Nuclear Facilities,” is available in ADAMS under Accession No. ML25329A088. The regulatory analysis for the RG can be found in ADAMS under Accession No. ML25329A089. Regulatory guides are not copyrighted, and NRC approval is not required to reproduce them.
NRC's PDR:
The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to
PDR.Resource@nrc.gov
or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
B. Submitting Comments
The NRC encourages electronic comment submission through the Federal rulemaking website (
https://www.regulations.gov). Please include Docket ID NRC-2025-0677 in your comment submission.
The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC will post all comment submissions at
https://www.regulations.gov
as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information.
If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment into ADAMS.
II. Discussion
The NRC is issuing, with a post-promulgation comment period, a RG in the NRC's “Regulatory Guide” series. This series was developed to describe methods that are acceptable to the NRC staff for implementing specific parts of the NRC's regulations, to explain techniques that the staff uses in evaluating specific issues or postulated events, and to describe information that the staff needs in its review of applications for permits and licenses.
The NRC staff is issuing Revision 0 of RG 1.220 to provide applicants and licensees of all types of nuclear facilities with an acceptable method for developing and implementing an IST program that would demonstrate compliance with NRC regulations for submission of an operating license or a combined operating license under part 50 of title 10 of the
Code of Federal Regulations
(10 CFR), “Domestic Licensing of Production and Utilization Facilities” or 10 CFR 52 “Licenses, Certification, and Approvals for Nuclear Power Plants,” respectfully. This RG endorses, with a regulatory position, the ASME Operation and Maintenance OM-2 Code for use by applicants of all types of nuclear facilities that may have different types of reactor and component designs.
The staff is also issuing a final regulatory analysis with a post-promulgation comment period (ADAMS Accession No. ML25329A089). The staff developed a regulatory analysis to assess the value of issuing an RG as well as an alternative course of action.
III. Post-Promulgation Comment Procedure
The NRC considers this action to be non-controversial, and is issuing this guidance document as a direct final RG with a 30-day post-promulgation comment period. This RG is effective on June 4, 2026. However, if the NRC receives comments that causes the NRC to make a change to this direct final RG by July 6, 2026, then the NRC will publish a
Federal Register
Notice that withdraws the guidance document and will address the comments received in a subsequent final RG or as otherwise appropriate.
IV. Congressional Review Act
This RG is a rule as defined in the Congressional Review Act (5 U.S.C. 801-808). However, the Office of Management and Budget has not found it to be a major rule as defined in the Congressional Review Act.
V. Backfitting, Forward Fitting, and Issue Finality
Issuance of RG 1.220 does not constitute backfitting as defined in 10 CFR 50.109, “Backfitting,” and as described in NRC Management Directive (MD) 8.4, “Management of Backfitting, Forward Fitting, Issue Finality, and Information Requests”; constitute
( printed page 33772)
forward fitting as that term is defined and described in MD 8.4; or affect the issue finality of any approval issued under 10 CFR part 52, “Licenses, Certifications, and Approvals for Nuclear Power Plants.” As explained in Revision 0 of RG 1.220, applicants and licensees generally are not required to comply with the positions in the RG.
VI. Submitting Suggestions for Improvement of Regulatory Guides
A member of the public may, at any time, submit suggestions to the NRC for improvement of existing RGs or for the development of new RGs. Suggestions can be submitted on the NRC's public website at
https://www.nrc.gov/reading-rm/doc-collections/reg-guides/contactus.html. Suggestions will be considered in future updates and enhancements to the “Regulatory Guide” series.
VII. Executive Order (E.O.) 12866
The Office of Information and Regulatory Affairs determined that this RG is not a significant regulatory action under E.O. 12866.
1 comment has been received at Regulations.gov.
Agencies review all submissions and may choose to redact, or withhold, certain submissions (or portions thereof). Submitted comments may not be available to be read until the agency has approved them.