This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
The hearing is scheduled to begin at 5:30 p.m. on August 13, 2026, at the Pollard Technology Conference Center auditorium located at 210 Badger Ave., Oak Ridge, TN 37830. This meeting will be preceded by an open house beginning at 5 p.m. at the same location.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
FederalRegister.gov retrieves relevant information about this document
from Regulations.gov to provide users with additional context. This
information is not part of the official Federal Register document.
Tennessee Valley Authority Clinch River Nuclear Site Exemption
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
457
as of
09/05/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2026-13662 as it appeared on Public Inspection on
07/06/2026 at 8:45 am.
It was viewed
9
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2026-13662 (91 FR 41664)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Construction permit application; notice of uncontested hearing.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC) is providing public notice of an uncontested hearing on a construction permit application from Tennessee Valley Authority for construction of Clinch River Nuclear Unit 1 at the Clinch River Nuclear Site in Roane County, Tennessee.
DATES:
The hearing is scheduled to begin at 5:30 p.m. on August 13, 2026, at the Pollard Technology Conference Center auditorium located at 210 Badger Ave., Oak Ridge, TN 37830. This meeting will be preceded by an open house beginning at 5 p.m. at the same location.
ADDRESSES:
Please refer to Docket ID NRC-2024-0146 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
Federal Rulemaking Website:
Go to
https://www.regulations.gov
and search for Docket ID NRC-2024-0146. Address questions about Docket IDs in
Regulations.gov
to Bridget Curran; telephone: 301-415-1003; email:
Bridget.Curran@nrc.gov.
For technical questions, contact the individual(s) listed in the
For Further Information Contact
section of this document.
NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly available documents online in the ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/adams.html.
To begin the search, select “Begin ADAMS Public Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to
PDR.Resource@nrc.gov.
NRC's PDR:
The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to
PDR.Resource@nrc.gov
or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT:
Allen Fetter, telephone: 301-415-8556; email:
Allen.Fetter@nrc.gov
and Ricky Vivanco, telephone: 301-415-0021; email:
Ricky.Vivanco@nrc.gov.
Both are staff of the Office of Advanced Reactors at the U. S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Discussion
By letter dated April 29, 2026 (ADAMS Accession Package No. ML26119A628), Tennessee Valley Authority (TVA or the applicant) submitted to the NRC revision 1 of a construction permit application under part 50 of title 10 of the
Code of Federal Regulations
(10 CFR), “Domestic Licensing of Production and Utilization Facilities,” for a small modular reactor (SMR) at the Clinch River Nuclear (CRN) site located in Oak Ridge, Roane County, Tennessee. The application is for a single-unit BWRX-300 SMR designated as Clinch River Nuclear Unit 1 (hereinafter also referred to as CRN-1). The BWRX-300 is a small modular boiling water reactor (BWR), designed by GE Vernova Hitachi Nuclear Energy (GVH), with a nominal electrical output of 300 megawatts-electric (MWe) and a thermal power rating of 870 megawatts thermal (MWt). The NRC staff Safety Evaluation Report is available in ADAMS under ML26168A505. The Environmental Report was included in Part 1 of the Clinch River Construction Permit Application and is available in ADAMS under ML25118A209. The NRC staff's Final Supplemental Environmental Impact Statement is available in ADAMS under ML26035A285.
Pursuant to Section 189a. of the Atomic Energy Act of 1954, as amended, and the Commission Policy Statement on Mandatory Hearings for Reactor Licensing (published in the
Federal Register
at 91 FR 34661), notice is hereby given that the uncontested (
i.e.,
mandatory) hearing will be held on August 13, 2026 starting at 5:30 p.m. in the Pollard Technology Conference Center auditorium located at 210 Badger Ave., Oak Ridge, TN 37830. Members of the public are invited to attend the hearing. There will be an opportunity for members of the public to ask questions and provide feedback on the application. This is not an opportunity to request a contested hearing, where petitioners can file intervention requests that contain the contentions they wish to litigate pursuant to 10 CFR 2.309. The opportunity to request a contested hearing and petition for leave to intervene was noticed on July 15, 2025, (90 FR 31709) and no intervention petitions were received.
An open house will be held before the hearing begins, from 5 to 5:30 p.m., to give the public an opportunity to speak with the NRC staff. The hearing will then convene at 5:30 p.m. and begin with a presentation by the NRC staff that will explain the review process and provide a brief overview of the application, followed by a comment period of up to 3 hours. During the comment period, the public will be provided an opportunity to speak on the record. Each member of the public will be allowed to speak for no more than five minutes at a time to ensure that all stakeholders who wish to provide oral
( printed page 41665)
comments or ask questions will have the opportunity to do so. The applicant has been made aware of the hearing and was invited to provide a presentation of no more than 30 minutes following the NRC staff presentation.
The hearing record for comments will remain open until August 27, 2026. Written comments must be submitted to the following email address:
ClinchRiver-CPHearing@nrc.gov.
In order to be included in the hearing record, written comments must be received by August 27, 2026. The NRC staff will not consider comments or questions received by other means or after the deadline of August 27, 2026. The NRC staff will treat any comments or questions received consistent with the Commission Policy Statement on Mandatory Hearings for Reactor Licensing.