This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
The EA and FONSI referenced in this document are available on August 24, 2026.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Comments are no longer being accepted.
See DATES for details.
Regulations.gov Data
Enhanced Content - Regulations.gov Data
FederalRegister.gov retrieves relevant information about this document
from Regulations.gov to provide users with additional context. This
information is not part of the official Federal Register document.
SMR, LLC Pioneer Units 1 and 2 Limited Work Authorization Application
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
234
as of
10/13/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2026-17253 as it appeared on Public Inspection on
08/24/2026 at 8:45 am.
It was viewed
23
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2026-17253 (91 FR 54890)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Notice; issuance.
( printed page 54891)
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC) is issuing an environmental assessment (EA) and finding of no significant impact (FONSI) for an exemption requested by SMR, LLC on behalf of Palisades SMR, LLC (Palisades SMR), associated with certain excavation support activities for the proposed dual-unit SMR-300 plant, Pioneer Units 1 and 2, at the Palisades Energy Center in Covert, Michigan. Specifically, Palisades SMR is requesting an exemption, pursuant to NRC regulations, to allow for construction of support of excavation (SOE) walls during SMR-300 excavation and prior to issuance of a Limited Work Authorization (LWA), if approved. Based on the analyses presented in the EA, the NRC staff determined that there would be no significant environmental impacts associated with granting the requested exemption.
DATES:
The EA and FONSI referenced in this document are available on August 24, 2026.
ADDRESSES:
Please refer to Docket ID NRC-2026-0265 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
Federal Rulemaking website:
Go to
https://www.regulations.gov
and search for Docket ID NRC-2026-0265. Address questions about Docket IDs in
Regulations.gov
to Bridget Curran; telephone: 301-415-1003; email:
Bridget.Curran@nrc.gov.
For technical questions, contact the individual listed in the
For Further Information Contact
section of this document.
NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly available documents online in the ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/adams.html.
To begin the search, select “Begin ADAMS Public Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to
PDR.Resource@nrc.gov.
The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document.
NRC's PDR:
The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to
PDR.Resource@nrc.gov
or call 1-800-397-4209 or 301-415- 4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT:
Robert Hoffman, Office of Advanced Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-1107; email:
Robert.Hoffman@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
By letter dated December 31, 2025 (ADAMS Package Accession No. ML25365A983), SMR, LLC, submitted the first part (Part 1) of a phased construction permit (CP) application to the NRC on behalf of Palisades SMR for a dual-unit SMR-300 plant, Pioneer Units 1 and 2, which would be co-located with the Palisades Nuclear Plant at the Palisades Energy Center in Covert, MI. The NRC determined that Part 1 of the phased construction permit CP application was acceptable for docketing on February 13, 2026 (ADAMS Accession No. ML26041A223).
Part 1 of the phased CP application includes a LWA request pursuant to paragraph 50.10(d) of title 10 of the
Code of Federal Regulations
(10 CFR), “Request for limited work authorization,” three exemption requests, and a comprehensive environmental report. The NRC is currently developing an environmental impact statement (EIS) to address the environmental impacts of construction, operation, and decommissioning of Pioneer Units 1 and 2, and expects to publish the draft EIS for public comment in the fall of 2026.
Part 1 of the phased CP application includes an exemption request from 10 CFR 50.10(c) to allow for construction of SOE walls, which would remain in place after construction is complete. The proposed exemption would allow Palisades SMR to proceed, prior to issuance of an LWA, if approved, with this limited construction activity. Palisades SMR has requested that the NRC consider and approve the exemption independently of, and prior to, completion of the NRC's review of the remainder of Part 1 of the phased CP application. Granting this exemption request would not constitute a commitment by the NRC to issue an LWA or CP for Pioneer Units 1 and 2, and Palisades SMR would perform the excavation support activities assuming the risk that its CP application may later be denied.
The NRC has prepared an EA (ADAMS Accession No. ML26230A249) as part of its review of the exemption request in accordance with the requirements of 10 CFR 51.21, “Criteria for and identification of licensing and regulatory actions requiring environmental assessments.” Based on the results of the EA, the NRC has determined not to prepare an EIS and is issuing a FONSI pursuant to 10 CFR 51.31.
II. Discussion
The proposed Federal action is NRC approval of Palisades SMR's request for an exemption from the NRC regulations at 10 CFR 50.10(c), which would allow construction of SOE walls during SMR-300 excavation and prior to issuance of an LWA, if approved by the NRC. Palisades SMR plans to install three different permanent retaining wall designs: diaphragm walls, soldier pile soil mixed walls, and perimeter cutoff walls. Tieback anchors would be used, as necessary, to support the differing wall designs. To accomplish the proposed Federal action, the reinforced concrete panel diaphragm walls, soldier pile soil mixed walls, and perimeter cutoff walls (all part of the SOE walls) would be installed using traditional construction techniques.
SOE walls would remain in place after construction is complete. Issuance of the exemption would allow Palisades SMR to proceed with SOE wall installation, prior to issuance of an LWA, if approved. Palisades SMR asserts that the SOE wall installation serves no function with respect to structural components of the containment structures (CS), reactor auxiliary building (RAB), or intermediate building (IB) support or radiological health or safety but is needed for construction worker safety during excavation. If excavation is delayed until after the issuance of the LWA, if approved by the NRC, activities for the below grade portions of the CS, RAB, IB and portions of select systems, structures, and components could add a significant time delay and construction costs to the Pioneer Units 1 and 2 project. Delaying the construction of Pioneer Units 1 and 2 could also delay the addition of 680 megawatts of energy and a reliable lower cost energy supply in the State of Michigan. Palisades SMR anticipates that the cost of any delay of the commercial operation of Pioneer Units 1 and 2 would be substantial.
In the EA, the NRC staff evaluated the proposed action to identify resource areas that could be affected and the potential for environmental impacts. This evaluation considered the nature and scope of the proposed activities and site-specific information. Based on this review, the NRC staff determined that the proposed action would not result in significant impacts to land use,
( printed page 54892)
terrestrial resources, aquatic resources, threatened and endangered species, air quality, nonradiological health, nonradioactive waste, socioeconomics, surface water, groundwater, historic and cultural resources, radiological human health and radiological waste management. Additionally, the NRC staff conducted consultation pursuant to Section 106 of the National Historic Preservation Act of 1966, as amended, independent of the NRC staff's National Environmental Policy Act environmental review. The NRC staff determined that the proposed action would result in No Historic Properties Affected, as defined in 36 CFR 800.4(d)(1).
The NRC staff also considered the alternative of denying the exemption request and determined that denial of the exemption request would avoid the environmental impacts discussed in this EA unless the NRC grants the applicant's request for an LWA in Part 1 of the phased CP application, in which case the impacts would then be delayed and incurred during LWA activities, if approved. A denial of this exemption and subsequent delay of the excavation-related activities, if the LWA is approved, could result in project costs and schedule delays to the Pioneer Units 1 and 2 project. Accordingly, the NRC staff determined that there are no alternatives that meet the need for the proposed action and that are environmentally preferable to the proposed action.
III. Finding of No Significant Impact
The proposed action before the NRC is whether to issue the exemption authorizing the construction of permanent SOE walls during excavation activities and prior to issuance of an LWA, if approved. As required by 10 CFR 51.21, the NRC prepared the EA. This FONSI incorporates by reference the EA summarized in Section II of this notice. Based on the analysis presented in the EA, the NRC staff has determined that the proposed action will not have a significant impact on the quality of the human environment. Accordingly, the NRC staff has determined that the preparation of an EIS is not required for the proposed Federal action and that a FONSI is warranted. This finding and the related environmental documents referenced throughout the EA are available for public review as discussed in the EA and above under
ADDRESSES
.