This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
The EA and FONSI referenced in this document are available on September 25, 2026.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Comments are no longer being accepted.
See DATES for details.
Regulations.gov Data
Enhanced Content - Regulations.gov Data
FederalRegister.gov retrieves relevant information about this document
from Regulations.gov to provide users with additional context. This
information is not part of the official Federal Register document.
Constellation Energy Generation, LLC; Christopher M. Crane Clean Energy Center; Applications for Amendments to Renewed Facility Operating License Involving Proposed No Significant Hazards Considerations and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
447
as of
10/13/2026 at 2:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2026-19603 as it appeared on Public Inspection on
09/24/2026 at 8:45 am.
It was viewed
28
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2026-19603 (91 FR 60988)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Notice; issuance.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC), as the lead agency, and the U.S. Department of Energy (DOE) Office of Energy Dominance Financing (EDF), as a cooperating agency, are issuing an environmental assessment (EA) and finding of no significant impact (FONSI) evaluating the reasonably foreseeable environmental effects from proposed Federal actions related to reauthorizing power operations at the Christopher M. Crane Clean Energy Center (CCEC). Specifically, the NRC is considering issuance of an exemption and three license amendments, which were requested by Constellation Energy Generation, LLC (CEG) to support the potential reauthorization of power operations at the CCEC. The DOE EDF's proposed action is a decision on providing Federal financial assistance (a loan guarantee) for refueling and resumption of power operations at the CCEC.
DATES:
The EA and FONSI referenced in this document are available on September 25, 2026.
ADDRESSES:
Please refer to Docket ID NRC-2026-0397 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
Federal Rulemaking Website:
Go to
https://www.regulations.gov
and search for Docket ID NRC-2026-0397. Address questions about Docket IDs in
Regulations.gov
to Bridget Curran; telephone: 301-415-1003; email:
Bridget.Curran@nrc.gov.
For technical questions, contact the individuals listed in the
FOR FURTHER INFORMATION CONTACT
section of this document.
NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly available documents online in the ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/adams.html.
To begin the search, select “Begin ADAMS Public Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to
PDR.Resource@nrc.gov.
For the convenience of the reader, instructions about obtaining materials referenced in this document are provided in the “Availability of Documents” section.
NRC's PDR:
The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to
PDR.Resource@nrc.gov
or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time, Monday through Friday, except Federal holidays.
NRC Public Project Website:
The EA and FONSI along with information regarding the CCEC, including licensing, operation, decommissioning, and potential restart, is available at
https://www.nrc.gov/info-finder/reactors/ccec.
FOR FURTHER INFORMATION CONTACT:
Kevin Folk, telephone: 301-415-6944; email:
Kevin.Folk@nrc.gov,
or Ashley Waldron, telephone: 301-415-7317; email:
Ashley.Waldron@nrc.gov.
Both are staff of the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Introduction
The CCEC, formerly Three Mile Island Nuclear Station, Unit 1 (TMI-1), consists of a single pressurized-water nuclear reactor located in Dauphin County, Pennsylvania, on Three Mile Island in the Susquehanna River. Originally licensed for operation on April 19, 1974, the NRC issued a renewed facility operating license (RFOL) for TMI-1 on October 22, 2009, with the license term expiring on April 19, 2034.
On June 20, 2017, and September 26, 2019, Exelon Generation Company, LLC, the licensee who then operated the facility, submitted certifications that it would permanently cease operations of TMI-1 and had permanently removed fuel from the reactor vessel, respectively, in accordance with paragraph 50.82(a)(1) of title 10 of the
Code of Federal Regulations
(10 CFR). Upon the NRC's docketing of these certifications, the RFOL no longer authorized operation of the reactor or emplacement or retention of fuel into the reactor vessel, as provided by 10 CFR 50.82(a)(2).
CEG is seeking to return the CCEC to power operations and has submitted for NRC approval an exemption request and three license amendment requests (LARs) in support of allowing the resumption of power operations through April 19, 2034, the previous expiration date of the facility's RFOL.
A notice of opportunity to request a hearing and petition for leave to intervene was published in the
Federal Register
on February 24, 2026, regarding the three LARs. Consistent with the Atomic Energy Act of 1954, as amended (the Act), and the NRC's regulations, the NRC did not publish a notice of opportunity for hearing on the exemption request.
The NRC staff prepared a draft EA and draft FONSI in accordance with 10 CFR 51.30, “Environmental assessment,” documenting its environmental review of the proposed actions related to reauthorizing power operations at the CCEC. The NRC staff issued the draft EA and draft FONSI with a notice in the
( printed page 60989)
Federal Register
and offered a 30-day public comment period in accordance with 10 CFR 51.33, “Draft finding of no significant impact; distribution.” The draft FONSI stated that the NRC staff had preliminarily determined that the proposed Federal actions will not have a significant effect on the quality of the human environment.
The environmental review included fulfillment of the NRC's obligations related to Section 106 of the National Historic Preservation Act of 1966, as amended (54 U.S.C. 300101,
et seq.) (NHPA). The regulation in 36 CFR 800.8, “Coordination with the National Environmental Policy Act,” allows agencies to use their National Environmental Policy Act of 1969 (42 U.S.C. 4321,
et seq.) process to fulfill the requirements of Section 106 of the NHPA. Therefore, pursuant to 36 CFR 800.8(c), the NRC used its process for the preparation of the EA on the proposed actions to comply with Section 106 of the NHPA in lieu of the procedures set forth at 36 CFR 800.3 through 800.6.
After consideration of the public comments, the NRC staff finalized the EA, which is summarized in Section II of this document. Based on this final EA and in accordance with 10 CFR 51.31, “Determinations based on environmental assessment,” the NRC staff has determined that the preparation of an environmental impact statement (EIS) is not necessary and has prepared a FONSI in accordance with 10 CFR 51.32, “Finding of no significant impact.” The FONSI is detailed in Section III of this document.
II. Summary of Environmental Assessment
Description of the Proposed Federal Actions and Need
The NRC's proposed actions are decisions on whether to grant or deny CEG's interdependent, connected licensing and regulatory requests, including any revisions or supplements thereto or other regulatory or licensing requests submitted to the NRC, that are necessary to support reauthorizing power operations and refueling of the CCEC reactor. The DOE EDF's proposed action is a decision on providing Federal financial assistance for refueling and resumption of power operations at the CCEC pursuant to CEG's loan guarantee agreement with the DOE that was issued pursuant to the Energy Policy Act (EPA) of 2005.
The need for the NRC proposed actions, which would collectively support the reauthorization of power operations and refueling of the CCEC under the existing RFOL, is to provide 835 megawatts-electric of baseload power generation capability to the Pennsylvania, New Jersey, and Maryland electric grid. In support of its decision to pursue the resumption of power operations at the CCEC, CEG cites a 20-year power purchase agreement signed in 2024 with Microsoft to supply carbon-free energy from the CCEC to Microsoft's data centers located within the PJM Interconnection LLC's electric grid. The need for the DOE proposed action (Federal financial assistance in the form of a loan guarantee) is to implement DOE's authority under Title XVII of the EPA of 2005, which was reauthorized, amended, and revised by the Inflation Reduction Act of 2022 (42 U.S.C. 16517) and the One Big Beautiful Bill Act (Pub. L. 119-21 (July 4, 2025)) to create the EDF Program. The purpose of the EDF Program is to finance projects and facilities in the United States that retool, repower, repurpose, or replace energy infrastructure that has ceased operations or enable operating energy infrastructure to increase capacity or output.
Environmental Impacts of the Proposed Federal Actions
In the EA, the NRC staff assessed the potential reasonably foreseeable environmental effects (impacts) from the proposed actions associated with the following relevant resource areas: land use and visual resources; meteorology, air quality, and noise; surface water resources; groundwater resources; ecological resources (terrestrial and aquatic); Federally protected ecological resources; historic and cultural resources; socioeconomic conditions; radiological and nonradiological human health; waste management; uranium fuel cycle and transportation; and postulated accidents. The NRC staff also considered decommissioning impacts as well as greenhouse gas emissions and climate change effects. The NRC staff determined that the environmental impacts of the proposed actions would be NOT SIGNIFICANT for each potentially affected environmental resource area. In addition, the NRC staff determined that the projected effects of climate change would not alter any of the impact determinations described in the EA.
Environmental Impacts of Alternatives to the Proposed Federal Actions
The NRC staff considered a reasonable range of alternatives to the proposed actions, including an analysis of any environmental impacts of not implementing the proposed actions (
i.e.,
the no-action alternative). The alternatives discussion in an EA does not need to be as extensive as would be required for an EIS. The NRC staff determined that there are no alternatives that meet the need for the proposed actions. For the no-action alternative, the NRC staff determined that the environmental impacts could potentially be SIGNIFICANT such as those associated with the construction and operation of new replacement power facilities. In contrast, the potential environmental impacts from the proposed actions of reauthorizing power operations at the existing CCEC would be NOT SIGNIFICANT for each potentially affected environmental resource area. Therefore, the NRC staff concluded that there are no environmentally preferrable alternatives to the proposed actions.
III. Finding of No Significant Impact
The proposed Federal actions before the NRC are whether to grant requests for an exemption and license amendments to support reauthorizing power operations at the CCEC through the remainder of its RFOL term (to April 19, 2034). The NRC staff has conducted an environmental review of these actions and prepared an EA. This FONSI incorporates by reference the EA summarized in Section II of this notice and referenced in Section IV of this notice. Based on its determination in the EA that the environmental impacts of the proposed actions would be NOT SIGNIFICANT for each potentially affected resource area, the NRC staff has determined that the proposed Federal actions will not have a significant effect on the quality of the human environment. Accordingly, the NRC staff has made a determination not to prepare an EIS for the proposed Federal actions and that a FONSI is warranted.
This FONSI and the related environmental documents referenced throughout this notice are available for public inspection as discussed in the EA and Section IV of this notice. At the conclusion of the NRC environmental review, the DOE EDF will publish a separate notice or decision document, as appropriate.
IV. Availability of Documents
The EA and related documents identified in the following table are available to interested parties through ADAMS, as indicated.
( printed page 60990)
Document description
ADAMS accession No.
Environmental Assessment and Finding of No Significant Impact for the Christopher M. Crane Clean Energy Center Reauthorization of Power Operations Project, dated September 18, 2026
ML26231A018.
Constellation Energy Generation, LLC; Christopher M. Crane Clean Energy Center; Draft Environmental Assessment and Draft Finding of No Significant Impact, dated June 8, 2026
Draft Environmental Assessment and Draft Finding of No Significant Impact for the Christopher M. Crane Clean Energy Center Reauthorization of Power Operations Project, June 2026
ML26120A058.
Constellation Energy Generation, LLC; Christopher M. Crane Clean Energy Center; Applications for Amendments to Renewed Facility License Involving Proposed No Significant Hazards Consideration Determination and Containing Safeguards Information and Order Imposing Procedures for Access to Safeguards Information; License amendment request (LAR); notice of opportunity to comment, request a hearing, and petition for leave to intervene; order imposing procedures, dated February 24, 2026