Under 28 CFR 50.7, notice is hereby given that on April 28, 2004, a proposed Consent Decree in
The complaint alleges that True violated the Clean Air Act in the (1) construction and operation of various modifications at its refrigeration manufacturing plant without obtaining a construction/operation permit as required by the federally approved Missouri New Source Review (“NSR”) Rules, codified at Rule 10 CSR 10–6.060
The Consent Decree settles these claims in exchange for payment of a civil penalty of $1,500,000 and True's performance of injunctive relief and three Supplemental Environmental Projects. True will remove the equipment for which it did not get the required permits and replace all of its solvent-based ink presses with presses that use ultraviolet light to cure ink, install three silk-screen cleaning machines that are enclosed systems with s solvent recovery system, and install a water filtration system.
The Department of Justice will receive for a period of thirty (30) days from the date of this publication comments relating to the Consent Decree. Comments should be addressed to the Assistant Attorney General, Environmental and Natural Resources Division, PO Box 7611, U.S. Department of Justice, Washington, DC 20044–7611, and should refer to
The Consent Decree may be examined at the Office of the United States Attorney, Eastern District of Missouri, 111 10th Street, St. Louis, MO 63102 and at U.S. EPA Region VII, U.S. EPA, Region VII, 901 N. 5th Street, Kansas City, KS 66101, (913) 551–7471. During the public comment period, the Consent Decree may also be examined on the following Department of Justice website,