k. With this notice, we are soliciting comments on the pre-filing materials listed in paragraph j above, including the draft license application and monitoring plans. All comments should be sent to the address above in paragraph h. In addition, all comments may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site
l. With this notice, we are approving Natural Currents' request to be designated as the non-federal representative for section 7 of the ESA and its request to initiate consultation under section 106 of the National Historic Preservation Act; and recommending that it begin informal consultation with: (a) The U.S. Fish and Wildlife Service and the National Marine Fisheries Service as required by section 7 of ESA; and (b) the New Jersey State Historic Preservation Officer, as required by section 106, National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2.
m. This notice does not constitute the Commission's approval of Natural Currents' request to use the Pilot Project Licensing Procedures. Upon its review of the project's overall characteristics relative to the pilot project criteria, the draft license application contents, any comments filed, and Natural Currents' response to any additional information requests by the Commission, the Commission will determine whether there is adequate information to conclude the pre-filing process and approve the use the Pilot Project Licensing Procedures.
n. The proposed Will's Hole Tidal Electric Project would consist of: (1) An approximately 50-foot by 20-foot floating dock structure that would be anchored by thirteen 12-inch diameter pilings; (2) two 7.9-foot-diameter Natural Currents Red Hawk Tidal generating units, with a total installed capacity of 40 kilowatts, each surrounded by a 5-foot by 11-foot stainless steel cage; (3) a 200-foot-long underwater transmission cable that would interconnect with the existing Jersey Central Power and Light system, and (4) appurtenant facilities for operating and maintaining the project. The project is estimated to have an annual generation of 70-megawatt-hours, which would be sold to the Kingsbridge Financial Group, Inc. and Will's Hole Marina.
o. A copy of the draft license application and all pre-filing materials are available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at
p. Pre-filing process schedule. The pre-filing process will be conducted pursuant to the following tentative schedule. Revisions to the schedule below may be made based on staff's review of the draft application and any comments received.