Notice of Availability for the Draft Environmental Impact Statement

Document Details

Information about this document as published in the Federal Register.

Published Document

This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Start Preamble

AGENCY:

Bureau of Land Management (BLM), Interior.

ACTION:

Notice of Availability for the Draft Environmental Impact Statement (EIS) on a proposed natural gas pipeline right-of-way.

SUMMARY:

Pursuant to section 102(2)(C) of the National Environmental Policy Act of 1969, the Bureau of Land Management (BLM), Coos Bay District, directed the preparation of a Draft EIS by Biological Information Specialists, Inc., a third party contractor on the impacts of a proposed natural gas pipeline from near Roseburg in Douglas County, Oregon, to Coos Bay in Coos County, Oregon. BLM received a right-of-way application under Section 501 of the Federal Land Policy and Management Act of October 21, 1976, (43 U.S.C. 1737) on May 17, 2000. The proposed pipeline will cross approximately 60 miles of public and private lands in Coos and Douglas Counties, Oregon. This notice initiates the public review process on the draft EIS. The public is invited to review and comment on the range and adequacy of the draft alternatives and associated environmental effects.

DATES:

The comment period will end 60 days after publication of the Environmental Protection Agency's Notice of Availability of this draft environmental impact statement in the Federal Register. Comments on the draft EIS should be received on or before the end of the comment period at the address listed below.

Public Participation: Public meetings will be held during the comment period. To ensure local community participation and input, public meetings will be held in Coos Bay, Oregon and at other locations if requested. Early participation by all those interested is Start Printed Page 66919encouraged. At least 15 days public notice will be given for activities where the public is invited to attend. All individuals, organizations, agencies, and Tribes with a known interest in this planning effort have been sent a copy of the document for review. Written comments will be accepted at the address shown below. For comments to be most helpful, they should relate to specific concerns or conflicts that are within the legal responsibilities of the BLM. Specific dates and locations of meetings and comment deadlines will be announced through the local news media, newsletters, and the BLM web site (www.or.blm.gov/​coosbay) and the Coos County web site (coosproj@att.net).

ADDRESSES:

Written comments should be sent to Bob Gunther, Project Coordinator, Coos Bay District, BLM, 1300 Airport Lane, North Bend, OR 97459. Documents pertinent to this proposal may be examined at the Coos Bay District Office in North Bend, Oregon and local libraries. Comments, including names and street addresses of respondents, will be available for public review at the Coos Bay District Office during regular business hours 7:45 a.m. to 4:30 p.m., Monday through Friday, except holidays, and may be published as part of the Final EIS. Individual respondents may request confidentiality. If you wish to withhold your name or street address from public review or from disclosure under the Freedom of Information Act, you must state this prominently at the beginning of your written comment. Such requests will be honored to the extent allowed by law. All submissions from organizations and businesses, and from individuals identifying themselves as representatives or officials of organizations or businesses, will be available for public inspection in their entirety.

Start Further Info

FOR FURTHER INFORMATION CONTACT:

Bob Gunther, Project Coordinator, at address above or telephone (541-751-4295), fax: 541-751-4303, or e-mail comments to the attention of Bob Gunther@or.blm.gov. For Technical Information contained in the EIS contact Brian Cox, Senior Biologist, Biological Information Specialists, Inc., P.O. Box 27, Camas Valley, Oregon 97416, Telephone: (541) 445-2008.

End Further Info End Preamble Start Supplemental Information

SUPPLEMENTARY INFORMATION:

The Coos County Board of Commissioners has applied for a right-of-way proposing to contract construction of a 12-inch natural gas transmission pipeline to be buried within the existing rights-of-ways of the Pacific Corp. (PP&L) and Bonneville Power Administration (BPA) electric transmission lines, and within the existing roadbed of the Coos Bay Wagon Road. The total length of the pipeline is approximately 60 miles, with approximately 3.0 miles located on lands administered by the BLM. The proposed pipeline would connect to the Williams Gas Pipeline at a meter facility southwest of Roseburg, in or near Section 33 Township 27 South, Range 6 West in Douglas County and would terminate at Ocean Boulevard in the city of Coos Bay (Section 27 Township 25 South, Range 13 West).

The natural gas transmission pipeline will deliver gas to distribution facilities built by Northwest Natural Gas in the Coos Bay and North Bend communities. Smaller 6-inch or 4-inch laterals will be built off the mainline to serve the cities of Coquille, Myrtle Point, and perhaps Bandon at a later date. The location of the laterals has not been finalized, but is anticipated to follow the location of existing power line, State highway, or railroad rights-of-way. Locations of the distribution lines within the city limits are not known at this time, but are anticipated to be located within existing road rights-of-way.

The proposed pipeline will fall under the jurisdiction of US Department of Transportation (DOT), as a gas transmission pipeline. It will be built and operated to all current specifications in 49 CFR Part 192 (Natural Gas Pipelines) and other relevant sections. The Oregon Public Utility Commission will administer DOT Pipeline Safety regulations for this pipeline.

The proposed pipeline will be designed with the appropriate design safety factors. The mainline is proposed as a welded steel pipeline with a Maximum Allowable Operating Pressure (MAOP) of 1,000 pounds per square inch (psi). The finished pipeline will be pressure tested to at least 150 percent of MAOP, to detect leakage or failure.

All construction is done during daylight hours. Mainline construction will take about 6 months. Applicant plans to construct in the relatively dry summer months of April through October.

Pipeline construction will require a working space up to 60 feet wide. DOT requires a minimum of 30 inches of cover in normal soils, 18 inches in consolidated rock, 36 inches under roads. The pipe will be installed to a target depth of 48 inches to top of pipe. Some grading will be required to install the pipe, but shall be substantially restored to original grade before revegetation. All earth disturbance operations shall be subject to an erosion control plan to comply with US Environmental Protection Agency (EPA) guidelines.

In sections along electrical transmission lines, the contractor shall be required to have and follow a plan to continuously ground the pipe, to protect workers from shock from induced currents.

Coos County plans to contract pipeline operations with an experienced pipeline operator. The County and its operator are required under DOT to formulate and use an Operations and Maintenance Plan specifically for this pipeline. The Operations and Maintenance Plan includes an Emergency Plan for specific procedures and notifications in case of an emergency.

Coos County plans to provide cathodic protection against corrosion, as required by DOT. Magnesium anodes will be placed at regular intervals along the pipeline, to sacrificially corrode and protect the coated steel pipe. This method normally mitigates most induced alternating current (AC). In sections near electrical transmission lines, supplemental anodes and other measures will be taken as necessary to minimize induced AC on the pipeline.

Long-term pipeline operation will require 40 feet of space to be kept clear of larger brush and trees. Access roads to the BPA corridor will be restored as needed for pipeline construction and access for Operations and Maintenance.

After the initial pipeline construction period, there is no need to ever excavate any particular segment of pipe. Annual maintenance consists of checking depth of pipe in roadways, repairing any soil erosion, controlling brush, replacing line markers, painting and operating block valves, conducting leak surveys, and checking the effectiveness of the corrosion control system.

The BLM considered issues and concerns identified during the scoping process in the preparation of the draft EIS. The issues identified include: socioeconomics impacts associated with the proposed project; soil erosion; water quality; fish, and wildlife; potential impacts to traditional Native American uses of the area, archaeological sites. Those individuals, organizations, and agencies with a known interest in the proposal will be sent a copy of the draft EIS. Persons wishing to be added to the mailing list for the EIS may do so by contacting the Coos Co. Pipeline Project Office, 1309 W. Central Blvd., Coquille, OR 97423. A final environmental impact Start Printed Page 66920statement is expected to be available for public review in early 2002.

Start Signature

Richard Conrad,

Acting District Manager.

End Signature End Supplemental Information