Start Preamble

AGENCY:

National Aeronautics and Space Administration.

ACTION:

Final rule.

SUMMARY:

This rule adopts as final, with a minor editorial change, the proposed rule published in the Federal Register (70 FR 33726-33727) on June 9, 2005. This final rule amends the NASA FAR Supplement (NFS) to add Alternate I to the “Major Breach of Safety or Security” clause. Alternate I deletes references to termination for default and makes other changes to be consistent with the FAR termination clauses prescribed for use with educational or nonprofit institutions performing research and development work on a nonprofit or no-fee basis, and in contracts for commercial items.

EFFECTIVE DATE:

February 22, 2006.

Start Further Info

FOR FURTHER INFORMATION CONTACT:

Carl Weber, Office of Procurement, Contract Management Division, (202) 358-1784, e-mail: carl.c.weber@nasa.gov.

End Further Info End Preamble Start Supplemental Information

SUPPLEMENTARY INFORMATION:

A. Background

Since July 13, 2000, NFS has required the Major Breach of Safety or Security clause (1852.223-75) in new solicitations and contracts with an estimated value over $500,000. The clause declares the Government's right to terminate for default in the event of a major breach of safety or security. However, contracts for commercial items procured under FAR Part 12 and certain contracts with educational or nonprofit institutions do not provide the Government the right to terminate for “default”. Commercial contracts provide rights to terminate for convenience and “cause”, and contracts with educational or nonprofit institutions provide the right to terminate for convenience.

NASA Procurement Information Circular (PIC 02-11) issued June 24, 2002, provided a class deviation to use an Alternate I to the clause, which deleted references to termination for default, under certain circumstances.

This final rule adds the Alternate I to the Major Breach of Safety or Security clause at 1852.223-75, eliminating the need for PIC 02-11 and the class deviation. Use of the clause with its Alternate I in contracts for commercial items procured under FAR Part 12, and contracts for research and development work with educational or nonprofit institutions on a nonprofit or no-fee basis will be consistent with FAR termination clauses prescribed for use in such contracts. NASA published a proposed rule in the Federal Register (70 FR 33726-33727) on June 9, 2005. No comments were received, and the proposed rule is being adopted with a minor editorial change to 1823.7001(d)(2)(ii) that simplifies the clause prescription to require it when FAR 52.212-4 is included in a solicitation or contract. This is not a significant regulatory action, and therefore, is not subject to Office of Management and Budget review under section 6(b), of Executive Order 12866, dated September 30, 1993. This is not a major rule under 5 U.S.C. 804.

B. Regulatory Flexibility Act

NASA certifies that this final rule does not have a significant economic impact on a substantial number of small entities with the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., since it only clarifies agency regulations so they are employed consistently with FAR termination provisions.

C. Paperwork Reduction Act

The Paperwork Reduction Act does not apply because the changes do not impose any new recordkeeping or information collection requirements which require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

Start List of Subjects

List of Subjects in 48 CFR Parts 1823 and 1852

End List of Subjects Start Signature

Tom Luedtke,

Assistant Administrator for Procurement.

End Signature Start Amendment Part

Accordingly,

End Amendment Part Start Part

PART 1823—ENVIRONMENT, ENERGY AND WATER EFFICIENCY, RENEWABLE ENERGY TECHNOLOGIES, OCCUPATIONAL SAFETY, AND DRUG-FREE WORKPLACE

End Part Start Amendment Part

1. The authority citation for

End Amendment Part Start Authority

Authority: 42 U.S.C. 2473(c)(1).

End Authority Start Amendment Part

2. Amend section 1823.7001 by revising paragraph (d) to read as follows:

End Amendment Part
NASA solicitation provisions and contract clauses.
* * * * *
Start Printed Page 8990

(d)(1) The contracting officer shall insert the clause at 1852.223-75, Major Breach of Safety or Security, in all solicitations and contracts with estimated values of $500,000 or more, unless waived at a level above the contracting officer with the concurrence of the project manager and the installation official(s) responsible for matters of security, export control, safety, and occupational health.

(2) Insert the clause with its Alternate I if—

(i) The solicitation or contract is with an educational or other nonprofit institution and contains the termination clause at FAR 52.249-5; or

(ii) The solicitation or contract is for commercial items and contains the clause at FAR 52.212-4.

(3) For contracts with estimated values below $500,000, use of the clause is optional.

* * * * *
Start Part

PART 1852—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

End Part Start Amendment Part

3. Amend section 1852.223-75 by adding Alternate I to read as follows:

End Amendment Part
Major Breach of Safety or Security.
* * * * *

Alternate I

(FEB 2006)

As prescribed in 1823.7001(d)(2), substitute the following paragraphs (a) and (b) for paragraphs (a) and (b) of the basic clause:

(a) Safety is the freedom from those conditions that can cause death, injury, occupational illness, damage to or loss of equipment or property, or damage to the environment. Safety is essential to NASA and is a material part of this contract. NASA's safety priority is to protect: (1) The public; (2) astronauts and pilots; (3) the NASA workforce (including contractor employees working on NASA contracts); and (4) high-value equipment and property. A major breach of safety may constitute a breach of contract that entitles the Government to exercise any of its rights and remedies applicable to material parts of this contract, including termination. A major breach of safety must be related directly to the work on the contract. A major breach of safety is an act or omission of the Contractor that consists of an accident, incident, or exposure resulting in a fatality or mission failure; or in damage to equipment or property equal to or greater than $1 million; or in any “willful” or “repeat” violation cited by the Occupational Safety and Health Administration (OSHA) or by a state agency operating under an OSHA approved plan.

(b) Security is the condition of safeguarding against espionage, sabotage, crime (including computer crime), or attack. A major breach of security may constitute a breach of contract that entitles the Government to exercise any of its rights and remedies applicable to material parts of this contract, including termination. A major breach of security may occur on or off Government installations, but must be related directly to the work on the contract. A major breach of security is an act or omission by the Contractor that results in compromise of classified information, illegal technology transfer, workplace violence resulting in criminal conviction, sabotage, compromise or denial of information technology services, equipment or property damage from vandalism greater than $250,000, or theft greater than $250,000.

End Supplemental Information

[FR Doc. 06-1572 Filed 2-21-06; 8:45 am]