This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Proposed Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Interested parties should submit written comments to the FAR Secretariat on or before February 12, 2007 to be considered in the formulation of a final rule.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
47
as of
10/07/2026 at 10:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCIES:
Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).
ACTION:
Proposed rule.
SUMMARY:
The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) are proposing to amend the Federal Acquisition Regulation (FAR) to implement recommendations to change the regulations related to performance-based payments (PBP).
DATES:
Interested parties should submit written comments to the FAR Secretariat on or before February 12, 2007 to be considered in the formulation of a final rule.
ADDRESSES:
Submit comments identified by FAR case 2005-016 by any of the following methods:
Federal eRulemaking Portal:http://www.regulations.gov. Search for any document by first selecting the proper document types and selecting “Federal Acquisition Regulation” as the agency of choice. At the “Keyword” prompt, type in the FAR case number (for example, FAR Case 2006-001) and click on the “Submit” button. Please include any personal and/or business information inside the document.You may also search for any document by clicking on the “Advanced search/document search” tab at the top of the screen, selecting from the agency field “Federal Acquisition Regulation”, and typing the FAR case number in the keyword field. Select the “Submit” button.
Fax: 202-501-4067.
Mail: General Services Administration, Regulatory Secretariat (VIR), 1800 F Street, NW, Room 4035, ATTN: Laurieann Duarte, Washington, DC 20405.
Instructions: Please submit comments only and cite FAR case 2005-016 in all correspondence related to this case. All comments received will be posted
( printed page 75187)
without change to
http://www.regulations.gov, including any personal and/or business confidential information provided.
FOR FURTHER INFORMATION CONTACT:
For clarification of content, contact Mr. Jerry Olson at (202) 501-3221. For information pertaining to status or publication schedules, contact the FAR Secretariat at (202) 501-4755. Please cite FAR case 2005-016.
SUPPLEMENTARY INFORMATION:
A. Background
The proposed changes to FAR 32.1000, 32.1003, 32.1004, 32.1005, and 32.1007 and the clause at 52.232-32 are intended to increase the use of performance-based payments as the method of contract financing on Federal Government contracts, and improve the efficiency of performance-based payments when used on these contracts. These proposed changes originated from recommendations submitted by the Department of Defense Performance-based Payments Working Group in their March 8, 2005 report. This is not a significant regulatory action and, therefore, was not subject to review under Section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
B. Discussion
The Councils are proposing to revise the following FAR provisions:
1. The current FAR 32.1001(e) is renumbered to (d) and rephrased to require payments to be made in accordance with each agency's policy.
2. FAR 32.1001(e) is moved from 32.1000 to clarify when use of PBPs is appropriate.
3. FAR 32.1003 is revised to specifically address when PBP's may be used. This revised language clarifies use of PBPs on fixed-priced line items and orders and on Indefinite Delivery-Indefinite Quantity and non-Indefinite Delivery contracts.
4. FAR 32.1004(a)(1), to clarify that events not requiring meaningful effort or action must not be included as events or criteria for PBPs. FAR 32.1004(a)(2)(iii), to specifically state that all cumulative events be identified. FAR 32.1004(b)(2)(ii) requires that the contracting officer must document the rationale for establishing a performance-based payment rate that is below the applicable progress payment rate. FAR 32.1004(c) is added (and the existing (c) renumbered) to clarify that the contracting officer shall not limit the amount of a PBP payment to a percentage of actual incurred cost for the scheduled event or performance criteria. FAR 32.1004(e)(1)(ii) is renumbered to 32.1004(f)(1)(ii) and revised to clarify that solicitations related to competitive source selections should state that the evaluation of the proposed prices will include an adjustment to reflect the estimated cost to the Government of providing each offeror's proposed PBP terms.
5. FAR 32.1007(a) is revised to clarify that the contracting officer responsible for administering the performance-based payments should also be responsible for reviewing, approving, and transmitting the payment requests to the payment office. FAR 32.1007(c) is revised to prohibit actual cost verification unless the purpose is to assist in establishing revised or new PBP milestones or values.
C. Regulatory Flexibility Act
The Councils do not expect this proposed rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601,
et seq., because this rule should reduce administrative costs for contractor and the Government, thus further encouraging the use of performance based payments. An Initial Regulatory Flexibility Analysis has, therefore, not been performed. We invite comments from small businesses and other interested parties. The Councils will consider comments from small entities concerning the affected FAR Parts 32 and 52 in accordance with 5 U.S.C. 610. Interested parties must submit such comments separately and should cite 5 U.S.C. 601,
et seq.
(FAR case 2005-016), in correspondence.
D. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the proposed changes to the FAR do not impose information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501,
et seq.
(d) Performance-based payments are contract financing payments and, therefore, are not subject to the interest-penalty provisions of prompt payment (see Subpart 32.9). These payments shall be made in accordance with agency policy.
(e) Performance-based payments shall not be used for—
(1) Payments under cost-reimbursement line items;
(2) Contracts for architect-engineer services or construction, or for shipbuilding or ship conversion, alteration, or repair, when the contracts provide for progress payments based upon a percentage or stage of completion; or
(3) Contracts awarded through sealed bid procedures.
(a) * * * (1) * * * The signing of contracts or modifications, the exercise of options, the passage of time, or other such occurrences do not represent meaningful efforts or actions and shall not be identified as events or criteria for performance-based payments. * * *
(2) * * *
(iii) The contract must specifically identify cumulative events or criteria and identify which events or criteria are preconditions for the successful achievement of each cumulative event or criterion.
(b) * * *
(2) Total performance-based payments shall—
(ii) * * * Unless otherwise provided in agency procedures, the contracting officer shall document the rationale for establishing the performance-based payment rate if the performance-based payment rate is less than the contractor's applicable progress payment rate.
(c)
Payment Amount. The contracting officer shall not limit the amount of a performance-based payment to a percentage of actual incurred cost for the scheduled event or performance criteria.
(f) * * *
(1) * * *
(ii) * * * Unless agencies prescribe other evaluation procedures, if the contracting officer anticipates that the cost of providing performance-based payments would have a significant impact on determining the best value offer, the solicitation should state that the evaluation of the offeror's proposed prices will include an adjustment to reflect the estimated cost to the Government of providing each offeror's proposed performance-based payments (see Alternate I to the provision at 52.232-28).
8. Amend section 32.1005 by—
a. Revising the introductory text of paragraph (a); and
b. Removing from paragraph (b)(2) “32.1004(e)” and adding “32.1004(f)” in its place.
Administration and payment of performance-based payments.
(a)
Responsibility. The contracting officer responsible for administering performance-based payments (see 42.302(a)(12)) for the contract shall review and approve all performance-based payments for that contract.
(c) * * * Reviews shall not include verification of actual cost unless the purpose is to assist in establishing revised or new performance-based payment milestones or values.
PART 52—SOLICITATION PROVISIONS AND CONTRACT CLAUSES
10. Amend section 52.232-32 by revising the date of the clause and the second sentence of paragraph (c)(2) to read as follows:
(2) * * * The designated payment office will pay approved requests on the _________ [
Contracting Officer insert day as prescribed by agency head; if not prescribed, insert “30th”] day after receipt of the request for performance-based payment by the designated payment office. * * *