Start Preamble Start Printed Page 22810

AGENCIES:

Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

ACTION:

Technical amendments.

SUMMARY:

This document makes amendments to the Federal Acquisition Regulation (FAR), Federal Acquisition Circular (FAC) 2005-32, published in the Federal Register at 74 FR 14622-14652, on March 31, 2009, in order to make editorial and correcting changes.

DATES:

Effective Date: May 14, 2009.

Start Further Info

FOR FURTHER INFORMATION CONTACT:

The Regulatory Secretariat, 1800 F Street, NW., Room 4041, Washington, DC 20405, (202) 501-4755, for information pertaining to status or publication schedule. Please cite FAC 2005-32, Technical Amendments.

End Further Info End Preamble Start Supplemental Information

SUPPLEMENTARY INFORMATION:

This document makes amendments to the Federal Acquisition Regulation (FAR), Federal Acquisition Circular (FAC) 2005-32, published in the Federal Register at 74 FR 14622-14652, on March 31, 2009, in order to make editorial and correcting changes.

Start List of Subjects

List of Subjects in 48 CFR Parts 5, 25, and 52

End List of Subjects Start Amendment Part

Therefore, DoD, GSA, and NASA amend

End Amendment Part Start Amendment Part

1. The authority citation for

End Amendment Part Start Authority

Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42 U.S.C. 2473(c).

End Authority Start Part

PART 5—PUBLICIZING CONTRACT ACTIONS

End Part
[Amended]
Start Amendment Part

2. Amend section 5.705 in the table that follows paragraph (b) by removing, from the second column, the heading “Posting Rationale on Special Section of Recovery.Gov” and adding “Rationale Required” in its place; and by removing, from the sixth row, second column, the colon and adding an em dash in its place.

End Amendment Part Start Part

PART 25—FOREIGN ACQUISITION

End Part Start Amendment Part

3. Amend section 25.200 by adding paragraph (c) to read as follows:

End Amendment Part
Scope of subpart.

(c) When using funds appropriated or otherwise provided by the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5) (Recovery Act) for construction, see Subpart 25.6.

Start Amendment Part

4. Amend section 25.1102 by removing from paragraph (c)(3) “other than Mexico” and adding “other than Bahrain, Mexico, and Oman” in its place; and revising paragraphs (e)(2)(i) and (e)(2)(ii) to read as follows:

End Amendment Part
Acquisition of construction.

(e) * * *

(2) * * *

(i) Basic clause. List all foreign construction materials excepted from the Buy American Act or section 1605 of the the Recovery Act, other than Recovery Act designated country construction material.

(ii) Alternate I. List in paragraph (b)(3) of the clause all foreign construction material excepted from the Buy American Act or section 1605 of the Recovery Act, unless the excepted foreign construction material is from a Recovery Act designated country other than Bahrain, Mexico, or Oman.

Start Part

PART 52—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

End Part
[Amended]
Start Amendment Part

5. Amend section 52.204-11 in paragraph (a), in the definition “Total Compensation” by removing the period after the paragraph (6) designation.

End Amendment Part Start Amendment Part

6. Amend section 52.212-5 by—

End Amendment Part Start Amendment Part

a. Revising the date of the clause;

End Amendment Part Start Amendment Part

b. Revising paragraphs (b)(3), (b)(16), and (b)(18);

End Amendment Part Start Amendment Part

c. Removing and reserving paragraph (e)(1)(iii); and

End Amendment Part Start Amendment Part

d. In Alternate II by—

End Amendment Part Start Amendment Part

1. Revising the date of the Alternate;

End Amendment Part Start Amendment Part

2. Redesignating paragraphs (e)(1)(ii)(B) through (e)(1)(ii)(M) as paragraphs (e)(1)(ii)(C) through (e)(1)(ii)(N), respectively; and adding a new paragraph (e)(1)(ii)(B); and

End Amendment Part Start Amendment Part

3. Removing from the newly designated paragraph (e)(1)(ii)(J) “2.222-51” and adding “52.222-51” in its place.

End Amendment Part Start Amendment Part

The revised and added text reads as follows:

End Amendment Part
Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Items.
* * * * *

CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS “(MAY 2009)”

(b) * * *

(3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (MAR 2009) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

__(16) 52.219-26, Small Disadvantaged Business Participation Program—Incentive Subcontracting (OCT 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).

__(18) 52.219-28, Post Award Small Business Program Rerepresentation (APR 2009) (15 U.S.C. 632(a)(2)).

* * * * *

Alternate II “(MAY 2009)”. * * *

(e)(1) * * *

(ii) * * *

(B) 52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (MAR 2009) (Section 1553 of Pub. L. 111-5).

Federal Acquisition Circular

Federal Acquisition Circular (FAC) 2005-32, Technical Amendments, is issued under the authority of the Secretary of Defense, the Administrator of General Services, and the Administrator for the National Aeronautics and Space Administration.

Unless otherwise specified, all Federal Acquisition Regulation (FAR) and other directive material contained in FAC 2005-32, Technical Amendments is effective May 14, 2009.

Start Signature
Start Printed Page 22811

Dated: May 5, 2009.

Amy G. Williams,

Acting Deputy Director, Defense Procurement and Acquisition Policy (Defense Acquisition Regulations System).

End Signature Start Signature

Dated: May 6, 2009.

Rodney P. Lantier,

Acting Senior Procurement Executive & Acting Deputy Chief Acquisition Officer, Office of the Chief Acquisition Officer, U.S. General Services Administration.

End Signature Start Signature

Dated: May 4, 2009.

William P. McNally,

Assistant Administrator for Procurement, National Aeronautics and Space Administration.

End Signature End Supplemental Information

[FR Doc. E9-11039 Filed 5-13-09; 8:45 am]