This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Classification for Lease and Subsequent Conveyance for Recreation and Public Purposes of Public Lands (N-94234) for a Park in the Southwest Portion of the Las Vegas Valley, Clark County, NV
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
77
as of
09/06/2026 at 12:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Bureau of Land Management, Interior.
ACTION:
Notice of availability.
SUMMARY:
The Bureau of Land Management (BLM) announces the availability of the Record of Decision (ROD) for the NextLight Renewable Power, LLC, Silver State Solar Project Environmental Impact Statement (EIS). The Department of the Interior Secretary signed the ROD on October 12, 2010, which constitutes the final decision of the Department.
ADDRESSES:
Copies of the ROD are available upon request from the BLM Southern Nevada District Office, 4701 N. Torrey Pines Drive, Las Vegas, Nevada 89130, or at the following Web site:
http://www.blm.gov/nv/st/en/fo/lvfo.html.
Copies of the ROD are also available for public inspection at the BLM Southern Nevada District Office and the BLM Nevada State Office, 1340 Financial Blvd., Reno, Nevada.
FOR FURTHER INFORMATION CONTACT:
Gregory Helseth, Renewable Energy Project Manager,
phone:
(702) 515-5173;
address:
BLM Southern Nevada District Office, 4701 N. Torrey Pines Drive, Las Vegas, Nevada 89130;
e-mail: Gregory_Helseth@blm.gov.
SUPPLEMENTARY INFORMATION:
The applicant, Nextlight Renewable Power, LLC, requested a right-of-way (ROW) authorization to construct, operate, maintain and decommission a 400-megawatt (MW) solar photovoltaic (PV) power plant and facilities. The Notice of Availability (NOA) for the Draft EIS analyzing impacts of the project and alternatives was released for public comment on April 16, 2010 (75 FR 19990). Four hundred eighty one comments were received on the Draft EIS. The comments were incorporated, where appropriate, to clarify the analysis presented in the Final EIS. The Environmental Protection Agency published the NOA for the Final EIS in the
Federal Register
on Friday, September 10, 2010 (75 FR 55326). The Final EIS analyzes 3 alternatives: A No Action Alternative, the Proposed Action, and a Modified Site Layout Alternative. These alternatives were shaped in part by comments received from the public and internal BLM review.
Alternative 1
—No Action Alternative. Under this alternative, the BLM would deny a ROW for construction, operation, maintenance, and decommission of a 400-MW solar photovoltaic power plant on public lands administered by the BLM.
Alternative 2
—Proposed Action. The Proposed Action Alternative is the construction, operation, maintenance and decommission of a solar facility utilizing passive PV technology. The project facilities would be constructed in 3 separate phases totaling 400-MW with a total surface disturbance of 2,967 acres. Phase 1 consists of a 60-MW direct current (50-MW alternating current) facility and is independent of the facilities identified in Phase 2 and Phase 3, which are inter-dependant facilities. Each facility component would be constructed as power purchase agreements and transmission infrastructure is in place and available to bring generated power to the market. Drainage controls would consist of a series of earthen drainage control berms that would contain surface runoff flows to existing primary drainages (storm water flow corridors) across the site.
Alternative 3
—Modified Site Layout Alternative. The Modified Site Layout
( printed page 64351)
Alternative is similar to the Proposed Action in development sequence and facilities, but contains additional drainage control structures to manage storm water run-off. Total surface disturbance for this alternative is 2,748 acres.
The ROD approves only the Phase 1 portion of Alternative 2, the Proposed Action. Phase 2 and Phase 3 of the Proposed Action are not authorized in the ROD and may be considered in the future when the necessary electric transmission upgrades are proposed. At that time, the BLM will prepare any necessary additional environmental review.