This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Notice of Availability To Distribute a Final Environmental Impact Statement (FEIS) for the Construction of a New Land Port of Entry in International Falls, MN
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Notice of Availability To Distribute a Final Environmental Impact Statement (FEIS) for the Construction of a New Land Port of Entry in International Falls, MN
Notice of Availability To Distribute a Final Environmental Impact Statement (FEIS) for the Construction of a New Land Port of Entry in International Falls, MN
Notice of Availability To Distribute a Final Environmental Impact Statement (FEIS) for the Construction of a New Land Port of Entry in International Falls, MN
01/27/2011
Notice of request for public comments regarding a new OMB information clearance.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
70
as of
10/09/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Public Buildings Service, General Services Administration (GSA).
ACTION:
Notice of availability.
SUMMARY:
The GSA announces its intent to distribute a FEIS under the National Environmental Policy Act (NEPA) of 1969 to assess the potential impacts from the construction and operation of a new land port of entry (LPOE) in International Falls, Minnesota (the “Proposed Action”).
DATES:
October 14, 2011.
FOR FURTHER INFORMATION CONTACT:
Donald R. Melcher, Jr., GSA Public Buildings Service, Great Lakes Region, Land Ports of Entry Service Center, 230 South Dearborn Street, Room 3600, Chicago, IL 60604, (312) 353-1237,
donald.melcher@gsa.gov.
SUPPLEMENTARY INFORMATION:
I. Background
At the request of Customs and Border Protection, the GSA is proposing to construct and operate a larger and improved LPOE which meets their needs and the design requirements of the GSA.
The existing facilities are undersized and functionally obsolete and, consequently, incapable of providing the level of security required. The Proposed Action includes: (a) Acquisition of adjoining land; (b) demolition of existing government structures at the existing LPOE; (c) construction of a main administration building and ancillary support buildings; and (d) incorporation of the principles of sustainable design through the Leadership in Energy and Environmental Design Green Building Rating System of the U.S. Green Building Council.
Alternatives studied include alternative locations and layouts for the components of the LPOE that are identified in the concurrent Feasibility Study including the main administration and ancillary support buildings, the associated transportation network, and parking. A no-build alternative also is being studied that evaluates the consequences of not constructing and operating the LPOE. This alternative is included to provide a basis for comparison to the action alternatives described above as required by the NEPA regulations (40 CFR 1002.14(d)).
The GSA announced the availability of the Draft EIS for the International Falls LPOE Improvements Study on January 14, 2010. A 45-day comment period immediately followed, during which the GSA invited Federal, State and local agencies, organizations and individuals to submit comments on the Draft EIS. A public hearing was held at the Rainy River Community College on January 27, 2010 and a transcript of the hearing was prepared. An advertisement for the public hearing appeared in International Falls'
The Daily Journal
on two occasions prior to the hearing and advertisements for the public hearing were placed at Boise, Inc., and other prominent locations. Two attendees offered substantive comments during the public hearing. The public hearing was preceded by an open house to allow attendees to view plans of the build alternatives in detail, review the Draft EIS and discuss its content with the GSA, and ask questions. The GSA received eight comment letters and one comment e-mail copies which are contained in the FEIS along with responses to the substantive comments.
After careful consideration of the comments received on the Draft EIS, the GSA identified Alternative 10 as best satisfying the proposed action's purpose and programmatic needs and has the least impact on the human and natural environment. Alternative 10 is identified as the Preferred Alternative in the FEIS and in the Record of Decision (ROD) subject also to Congressional
( printed page 63924)
authorization and appropriation of availability of funds, GSA control of the site to complete archaeological investigations and continuity of the tenant agencies' Program of Requirements as they were understood at the time this study was completed.
Following this thirty (30) day notice in the Federal Register, the GSA will issue a ROD at which time its availability will be announced in the
Federal Register
and local media.
II. Distribution
Copies of the FEIS are being distributed to select stakeholders as well as being made available for public review at the International Falls Public Library, Chamber of Commerce Offices, and Koochiching County Office Building.
Dated: October 6, 2011.
Ann P. Kalayil,
Regional Commissioner, Public Buildings Service, Great Lakes Region.