This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Proposed Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Interested parties should submit written comments to the Regulatory Secretariat at one of the addressees shown below on or before September 9, 2014 to be considered in the formation of the final rule.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
1,593
as of
08/11/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2014-16149 as it appeared on Public Inspection on
07/09/2014 at 8:45 am.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2014-16149 (79 FR 39361)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).
ACTION:
Proposed rule.
SUMMARY:
DoD, GSA, and NASA are proposing to amend the Federal Acquisition Regulation (FAR) to implement section 802 of the National Defense Authorization Act of Fiscal Year 2013. This section provides additional requirements relative to the review and justification of Pass-Through contracts.
DATES:
Interested parties should submit written comments to the Regulatory Secretariat at one of the addressees shown below on or before September 9, 2014 to be considered in the formation of the final rule.
ADDRESSES:
Submit comments in response to FAR Case 2013-012 by any of the following methods:
Regulations.gov: http://www.regulations.gov.
Submit comments via the Federal eRulemaking portal by searching for “FAR Case 2013-012”. Select the link “Comment Now” that corresponds with “FAR Case 2013-012.” Follow the instructions provided at the “Comment Now” screen. Please include your name, company name (if any), and “FAR Case 2013-012” on your attached document.
Fax:
202-501-4067.
Mail:
General Services Administration, Regulatory Secretariat (MVCB), ATTN: Ms. Flowers, 1800 F Street NW., 2nd Floor, Washington, DC 20405.
Instructions:
Please submit comments only and cite FAR Case 2013-012, in all correspondence related to this case. All comments received will be posted without change to
http://www.regulations.gov,
including any personal and/or business confidential information provided.
FOR FURTHER INFORMATION CONTACT:
Mr. Edward N. Chambers, Procurement Analyst, at 202-501-3221, for clarification of content. For information pertaining to status or publication schedules, contact the Regulatory Secretariat at 202-501-4755. Please cite FAR Case 2013-012.
SUPPLEMENTARY INFORMATION:
I. Background
The National Defense Authorization Act (NDAA) for Fiscal Year 2013 was signed into law and effective on December 31, 2012. Section 802 of the law provides additional requirements relative to the review and justification of Pass-Through contracts. Specifically, this law requires in those instances where an offeror for a contract, task order, or delivery order informs the agency pursuant to FAR 52.215-22 of their intention to award subcontracts for more than 70 percent of the total cost of work to be performed under the contract, task order, or delivery order, the contracting officer is required to (1) consider the availability of alternative contract vehicles and the feasibility of contracting directly with a subcontractor or subcontractors that will perform the bulk of the work; (2) make a written determination that the contracting approach selected is in the best interest of the Government; and (3) document the basis for such determination. Therefore, FAR 15.404-1(h) is being created by this rule to implement these statutory requirements.
However, Section 1615 of the NDAA for Fiscal Year 2014, which was signed into law and effective on December 26, 2013, provides that for contracts under the provisions of Section 46 of the Small Business Act (15 U.S.C. 657s) the requirements under Section 802 of the NDAA for Fiscal Year 2013 do not apply. Accordingly, the proposed rule exempts FAR Part 19 acquisitions.
While Section 802 only applies to contracts with the Department of Defense, the Department of State, and the United States Agency for International Development, for the purpose of consistency, it was decided to apply the section's requirements to all of the agencies subject to the FAR.
II. Executive Orders 12866 and 13563
Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is a significant regulatory action and, therefore, was subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
III. Regulatory Flexibility Act
DoD, GSA, and NASA do not expect this proposed rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601,
et seq., because the rule augments the current responsibilities of contracting officers relative to the review and justification of pass-through contracts and does not initiate or impose any new administrative or performance requirements on contractors.
Therefore, an Initial Regulatory Flexibility Analysis has not been performed. DoD, GSA, and NASA invite comments from small business entities concerns and other interested parties on the expected impact of this rule on small entities.
DoD, GSA, and NASA will also consider comments from small entities concerning the existing regulations in subparts affected by the rule consistent with 5 U.S.C. 610. Interested parties
( printed page 39362)
must submit such comments separately and should cite 5 U.S.C. 610, FAR Case 2013-012, in correspondence.
IV. Paperwork Reduction Act
This rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C chapter 35).
(h)
Review and justification of pass-through contracts.
(1) The requirements of this paragraph (h) are applicable to all agencies. The requirements apply by law to the Department of Defense, the Department of State, and the United States Agency for International Development, per Section 802 of the National Defense Authorization Act (NDAA) for Fiscal Year 2013. The requirements apply as a matter of policy to other Federal agencies.
(2) Except as provided in paragraph (h)(3) of this section, when an offeror for a contract or a task or delivery order informs the contracting officer pursuant to 52.215-22 that it intends to award subcontracts for more than 70 percent of the total cost of work to be performed under the contract, task or delivery order, the contracting officer shall—
(i) Consider the availability of alternative contract vehicles and the feasibility of contracting directly with a subcontractor or subcontractors that will perform the bulk of the work;
(ii) Make a written determination that the contracting approach selected is in the best interest of the Government; and
(iii) Document the basis for such determination.
(3) Contract actions under FAR Part 19 are exempt from the requirements of this paragraph (h).