Information Collection Requirement; Defense Federal Acquisition Regulation Supplement; Earned Value Management System; Submission for OMB Review; Comment Request

Document Details

Information about this document as published in the Federal Register.

Document Statistics
Document page views are updated periodically throughout the day and are cumulative counts for this document including its time on Public Inspection. Counts are subject to sampling, reprocessing and revision (up or down) throughout the day.
Enhanced Content

Relevant information about this document from Regulations.gov provides additional context. This information is not part of the official Federal Register document.

Published Document

This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Start Preamble

AGENCY:

Defense Acquisition Regulations System, Department of Defense (DoD).

ACTION:

Notice.

SUMMARY:

The Defense Acquisition Regulations System has submitted to OMB for clearance, the following proposal for collection of information under the provisions of the Paperwork Reduction Act.

DATES:

Consideration will be given to all comments received by June 22, 2018.

End Preamble Start Supplemental Information

SUPPLEMENTARY INFORMATION:

Title, Associated Form, and OMB Number: Defense Federal Acquisition Regulation Supplement (DFARS) Business Systems-Definition and Administration; DFARS 234, Earned Value Management System, OMB Control Number 0704-0479.

Affected Public: Businesses and other for-profit entities.

Respondent's Obligation: Required to obtain or retain benefits.

Type of Request: Revision of a currently approved collection.

Reporting Frequency: On occasion.

Number of Respondents: 10.

Responses per Respondent: 1.

Annual Responses: 10.

Average Burden per Response: 676 hours.

Annual Response Burden Hours: 6,760.

Needs and Uses: DFARS clause 252.242-7005, Contractor Business Systems, requires contractors to respond to written determinations of significant deficiencies in the contractor's business systems as defined in the clause. The information contractors are required to submit in response to findings of significant deficiencies in their accounting system, estimating system, material management and accounting system, and purchasing system has previously been approved by the Office of Management and Budget. This request specifically addresses information required by DFARS clause 252.234-7002, Earned Value Management System, for contractors to respond to determinations of significant deficiencies in a contractor's Earned Value Management System (EVMS). The requirements apply to entities that are contractually required to maintain an EVMS. DoD needs this information to document actions to correct significant deficiencies in contractor business systems. DoD contracting officers use the information to mitigate the risk of unallowable and unreasonable costs being charged on government contracts.

OMB Desk Officer: Ms. Jasmeet Seehra.

Comments and recommendations on the proposed information collection should be sent to Ms. Jasmeet Seehra, DoD Desk Officer, at Oira_submission@omb.eop.gov. Please identify the proposed information collection by DoD Desk Officer and the Docket ID number and title of the information collection

You may also submit comments, identified by docket number and title, by the following method:

Federal eRulemaking Portal: http://www.regulations.gov. Follow the instructions for submitting comments.

DoD Clearance Officer: Mr. Frederick C. Licari.

Written requests for copies of the information collection proposal should be sent to Mr. Licari at: WHS/ESD Directives Division, 4800 Mark Center Drive, 2nd Floor, East Tower, Suite 03F09, Alexandria, VA 22350-3100.

Start Signature

Amy G. Williams,

Deputy, Defense Acquisition Regulations System.

End Signature End Supplemental Information

[FR Doc. 2018-10906 Filed 5-22-18; 8:45 am]