During the funding lapse, Federalregister.gov is not being supported. If data feeds are not available from GPO, FederalRegister.gov will not be updated, so please use the official edition of the Federal Register on Govinfo (https://www.govinfo.gov/app/collection/fr). If there is a technical issue with the Public Inspection List, you can view the documents on public inspection at our office in Washington, DC or on archives.gov.

Notice

Swan Lake North Hydro LLC; Notice of Modification of Procedural Schedule

Document Details

Information about this document as published in the Federal Register.

Document Statistics
Document page views are updated periodically throughout the day and are cumulative counts for this document including its time on Public Inspection. Counts are subject to sampling, reprocessing and revision (up or down) throughout the day.
Published Document

This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Start Preamble

Take notice that the schedule for processing the following hydroelectric application has been modified.

a. Type of Application: Original License (Major Project).

b. Project No.: 13318-003.

c. Date Filed: October 28, 2015.

d. Applicant: Swan Lake North Hydro LLC.

e. Name of Project: Swan Lake North Pumped Storage Hydroelectric Project.

f. Location: The project would be located about 11 miles northeast of Klamath Falls, in Klamath County, Oregon. The project would occupy about 730 acres of federal lands administered by the Bureau of Land Management and the Bureau of Reclamation, state lands, and private lands.

g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).

h. Applicant Contact: Erik Steimle, Rye Development LLC, 745 Atlantic Avenue, 8th Floor, Boston, MA 02111. Telephone: (503) 998-0230; Email: erik@ryedevelopment.com.

i. FERC Contact: Dianne Rodman at (202) 502-6077 or dianne.rodman@ferc.gov.

j. Procedural Schedule: The Commission's December 20, 2017 Notice of Application Ready for Environmental Analysis established August 2018 as the estimated date for issuing the Draft Environmental Impact Statement (EIS). The revised estimate for issuing the Draft EIS is now September 2018. As such, the application will be processed according to the following revised schedule. Revisions to the schedule may be made as appropriate. If a date falls on a weekend or holiday, the due date will be the following business day.

MilestoneTarget date
Commission Issues Draft EISSeptember 2018.
Comments on Draft EISNovember 2018.
Commission Issues Final EISJanuary 2019.
Start Signature

Dated: July 13, 2018.

Kimberly D. Bose,

Secretary.

End Signature End Preamble

[FR Doc. 2018-15485 Filed 7-19-18; 8:45 am]