This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
379
as of
08/13/2026 at 12:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2019-02526 as it appeared on Public Inspection on
02/14/2019 at 8:45 am.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2019-02526 (84 FR 4371)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Defense Acquisition Regulations System, Department of Defense (DoD).
ACTION:
Final rule.
SUMMARY:
DoD is issuing a final rule to amend the Defense Federal Acquisition Regulation Supplement (DFARS) to implement a section of the National Defense Authorization Act for Fiscal Year 2018 that provides an exemption from design-build selection procedures for contracts that exceed $4 million.
DATES:
Effective February 15, 2019.
FOR FURTHER INFORMATION CONTACT:
Ms. Heather Kitchens, telephone 571-372-6104.
SUPPLEMENTARY INFORMATION:
( printed page 4372)
I. Background
DoD published a proposed rule in the
Federal Register
at 83 FR 42850 on August 24, 2018, to implement section 823 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2018. Section 823 modifies 10 U.S.C. 2305a to provide an exemption from the phase two design-build maximum number of offerors that may be selected to submit competitive proposals for contracts exceeding $4 million. The exemption provides that if the contract value exceeds $4 million and the solicitation is issued pursuant to an indefinite-delivery indefinite-quantity (IDIQ) contract for design-build construction, the maximum number of offerors to be selected may exceed five.
In addition, for other than IDIQ contracts, the rule provides authority to exceed the five offeror maximum when the contracting officer's decision is approved by the head of the contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity, when the solicitation is for a contract that exceeds $4 million. When a solicitation is for a contract that does not exceed $4 million, the rule provides that the number of offerors is at the contracting officer's discretion.
Three respondents submitted public comments in response to the proposed rule.
II. Discussion and Analysis
DoD reviewed the public comments in the development of the final rule. A discussion of the comments received and any changes made to the rule are provided as follows:
A. Summary of Significant Changes
There were no changes from the proposed rule made in the final rule as a result of the comments received. The comments did not recommend changes to the proposed rule; rather, the respondents expressed concerns over the underlying intent of the statute.
B. Analysis of Public Comments
1. Administrative and Cost Burden
Comment:
Several respondents stated that the statutory requirement will create a significant administrative and cost burden on the Government and/or industry. One respondent suggested that the exemption will require DoD officials to review an unnecessarily high number of full proposals undermining the purpose of both IDIQ contracts and design-build.
Response:
The rule does not require contracting officers to consider more than five offerors; instead, the rule provides contracting officers the option to allow for more than five offerors to submit competitive proposals in solicitations for contracts for design-build construction that exceed $4 million.
2. Impact on Competition
Comment:
Several respondents stated that the statutory requirement will drive away highly qualified design-build firms and/or possibly favor lower qualified firms. One respondent stated that increasing the number of offerors will reduce participation from highly qualified firms who incur much of the cost in these competitions. The same respondent noted that increasing the number of offerors may favor lower qualified offerors based on artificially low bids.
Response:
DoD does not agree that the statutory requirement, and the resulting implementing rule, will drive away highly qualified design-build firms and/or possibly favor lower qualified firms. The competitive selection criteria will not change based on this rule. Conversely, the rule could be viewed as providing expanded opportunity for qualified firms to compete.
3. Learning Curve
Comment:
One respondent stated that the statutory requirement will create a learning curve for new firms, which will result in longer project times.
Response:
DoD does not agree that expanding the competitive pool will necessarily result in longer project times. While a learning curve might be expected for any new firm or new requirement, this does not drive the decision of whether or not to restrict competition.
4. Industry Best Practices/Innovation
Comment:
Two respondents stated that the statutory requirement moves away from industry best practices. One respondent stated that the statutory requirement diminishes the opportunities for innovation that design-build offers.
Response:
While the rule may be viewed by the respondents as moving away from industry best practices, this rule is necessary to meet the requirements of the statute. Opening up the competitive pool may result in opportunities for increased innovation.
5. Accountability
Comment:
One respondent stated that the statutory requirement will create a larger competitive pool which will diminish accountability.
Response:
Opening up the competitive pool should not have any effect upon or diminish accountability.
C. Other Changes
One minor editorial change is made to the rule numbering to correctly designate the added DFARS rule text as “236.303-1(a)(4)” in lieu of “236.303-1(4)”.
III. Applicability to Contracts at or Below the Simplified Acquisition Threshold and for Commercial Items, Including Commercially Available Off-the-Shelf Items
This rule does not create any new provisions or clauses or impact any existing provisions or clauses.
IV. Executive Orders 12866 and 13563
Executive Order (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This is not a major rule under 5 U.S.C. 804.
This final rule is not an E.O. 13771 regulatory action, because this rule is not significant under E.O. 12866.
VI. Regulatory Flexibility Act
A final regulatory flexibility analysis has been prepared and is summarized as follows:
This rule amends the Defense Federal Acquisition Regulation Supplement (DFARS) to implement section 823 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2018, which modifies 10 U.S.C. 2305a(d) regarding the maximum number of offerors that may be selected to submit competitive proposals under solicitations for two-phase design-build. Specifically, the selection procedures are modified by providing an exemption from the maximum number of five offerors when the contract value in a solicitation exceeds $4 million and the solicitation is issued pursuant to an indefinite-delivery indefinite-quantity (IDIQ) contract for design-build construction. The rule provides the
( printed page 4373)
authority to exceed the five offeror maximum when the contracting officer's decision is approved by the head of the contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity, when the solicitation is for a contract that exceeds $4 million. The rule also provides that the number of offerors is at the contracting officer's discretion when the solicitation is for a contract that does not exceed $4 million.
There were no significant issues raised by the public comments in response to the initial regulatory flexibility analysis.
Based on FY 2017 data from the Federal Procurement Data System, DoD issued approximately 499 new awards for construction exceeding $4 million to 396 unique businesses, to include IDIQ contracts, purchase orders, and orders under basic ordering agreements. Of the 499 new awards for construction, approximately 305 awards (approximately 61 percent) were made to 252 unique small entities (approximately 64 percent). This estimate is based on the assumption that contracts for design-build are coded as “construction” in FPDS, in which case a smaller number of small entities are actually impacted by the opportunity to exceed to the five offeror maximum for contracts valued in excess of $4 million. For contracts valued at or below $4 million, the FAR already provides an opportunity for contracting officers to determine that a greater number of offerors is in the Government's interest and is consistent with the purposes and objectives of the two-phase design-build selection procedures. No significant impact is expected to result from authorizing contracting officers to exceed the maximum number at their own discretion.
This final rule does not include any new reporting or recordkeeping requirements for small entities.
There are no known significant alternative approaches to the final rule that would meet the requirements of the applicable statute.
VI. Paperwork Reduction Act
The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).
(a)(4) In lieu of the limitations on the maximum number of offerors that may be selected to submit phase-two proposals at FAR 36.303-1(a)(4), for DoD—
(i) If the contract value exceeds $4 million, the maximum number of offerors specified in the solicitation that are to be selected to submit phase-two proposals shall not exceed five, unless—
(A) The solicitation is issued for an indefinite-delivery indefinite-quantity contract for design-build construction; or
(B) The head of the contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity, approves the contracting officer's decision with respect to an individual solicitation, that a maximum number greater than five is in the best interest of the Government and is consistent with the purposes and objectives of the two-phase selection procedures. The decision shall be documented in the contract file (10 U.S.C 2305a(d)).
(ii) If the contract value is at or below $4 million, the maximum number of offerors specified in the solicitation that are to be selected to submit phase-two proposals is at the discretion of the contracting officer.