This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants (NUREG-0654/FEMA-REP-1, Rev. 2)
This final guidance document is available on December 23, 2019.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
355
as of
06/07/2026 at 12:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2019-27435 as it appeared on Public Inspection on
12/20/2019 at 8:45 am.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2019-27435 (84 FR 70399)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Final guidance; issuance.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC), concurrently with the Federal Emergency Management Agency (FEMA), is issuing final guidance document entitled, “Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants; Rev. 2” (NUREG-0654/FEMA-REP-1, Rev. 2).
DATES:
This final guidance document is available on December 23, 2019.
ADDRESSES:
Please refer to Docket ID NRC-2018-0261 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
Federal Rulemaking Website:
Go to
https://www.regulations.gov
and search for Docket ID NRC-2018-0261 or FEMA-2012-0026. Address questions about NRC docket IDs in
Regulations.gov
to Jennifer Borges; telephone: 301-287-9127; email:
Jennifer.Borges@nrc.gov.
Public comments and supporting materials related to this final guidance document can be found at
https://www.regulations.gov
by searching on Docket ID FEMA-2012-0026. For technical questions, contact the individual listed in the
FOR FURTHER INFORMATION CONTACT
section of this document.
NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly available documents online in the ADAMS Public Document collection at
https://www.nrc.gov/reading-rm/adams.html.
To begin the search, select “
Begin Web-based ADAMS Search.
” For problems with ADAMS, contact the
( printed page 70400)
NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to
pdr.resource@nrc.gov.
NUREG-0654/FEMA-REP-1, Rev. 2, “Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants,” Final Report is available in ADAMS under Accession No. ML19347D139.
NRC's PDR:
You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Jonathan Fiske, Office of Nuclear Security and Incident Response, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-287-9228, email:
Jonathan.Fiske@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
In November 1980, the NRC and FEMA issued “Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants; Rev. 1” (NUREG-0654/FEMA-REP-1, Rev. 1) as a joint interagency guidance document (45 FR 85862; December 30, 1980). NUREG-0654/FEMA-REP-1, Rev. 1 provides guidance on the 16 Planning Standards referenced in the NRC's regulations in § 50.47 of title 10 of the
Code of Federal Regulations
(10 CFR), and in FEMA's regulations at 44 CFR 350.5. Both agencies use these Planning Standards, and the associated Evaluation Criteria contained in NUREG-0654/FEMA-REP-1, Rev. 1, to evaluate the adequacy of emergency plans and preparedness of commercial nuclear power plant owners and operators, and state, local, and tribal government jurisdictions located near commercial nuclear power plant sites.
Since the publication of NUREG-0654/FEMA-REP-1, Rev. 1, there have been substantial changes to NRC and FEMA regulations, guidance, and policies and advances in emergency preparedness planning and technology. As a result, the NRC and FEMA have issued four supplementary documents and one addendum to update and expand upon the guidance in NUREG-0654/FEMA-REP-1, Rev 1. This revision consolidates the four supplementary documents and one addendum, and provides updates and additional guidance reflective of over 35 years of improvements and lessons learned in the radiological emergency preparedness community.
The NRC and FEMA held two public meetings on August 22, 2012, and September 13, 2012, to discuss the scope of the proposed revision to NUREG-0654/FEMA-REP-1, Rev. 1 (77 FR 46766; August 6, 2012). To assist in further defining the scope, the NRC and FEMA solicited public comments on specific issues related to NUREG-0654/FEMA-REP-1, Rev. 1 (77 FR 65700; October 30, 2012). Additionally, stakeholder and public engagement sessions were held during staff development of the revised guidance on October 29-31, 2013 and June 25, 2014.
Following development of the revised guidance, the draft NUREG-0654/FEMA-REP-1, Rev. 2 was posted to the Federal Rulemaking website at
https://www.regulations.gov
for public comment (80 FR 30697; May 29, 2015). The original 90-day comment period was scheduled to conclude on August 27, 2015; however, in response to requests from the public for an extension based on the broad scope of the revision and the extensive review necessary to develop comments, the NRC and FEMA granted a 45-day extension to the original comment period (80 FR 50862; August 21, 2015). The comment period closed on October 13, 2015. In total, the agencies received, reviewed, and considered 609 comments during development of this revision. Of the 609 comments, 64 were accepted (draft guidance was revised exactly as recommended), 154 were agreed to in part, and the remaining 391 were either noted or rejected. In all, 218 comments resulted in revisions to the draft guidance. A detailed report on the comment resolutions, including the agencies' rationales for each comment's disposition, will be available online for review in ADAMS under Accession No. ML19350A378 and at
https://www.regulations.gov/,
under Docket ID NRC-2018-0261, within 30 days after issuance of the final NUREG-0654/FEMA-REP-1, Rev. 2.
II. Congressional Review Act
The NUREG-0654/FEMA-REP-1, Rev. 2 is a rule as defined in the Congressional Review Act (5 U.S.C. 801-808). However, the Office of Management and Budget has not found it to be a major rule as defined in the Congressional Review Act.
Dated at Rockville, Maryland, this 16th day of December, 2019.
For the Nuclear Regulatory Commission.
Brian E. Holian,
Director, Office of Nuclear Security and Incident Response.