This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Notice
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
Notice of Intent To Prepare a Supplemental Environmental Impact Statement for Updates to the Implementation of Howard A. Hanson Dam Downstream Fish Passage, Washington
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
315
as of
08/14/2026 at 4:15 am EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2021-20240 as it appeared on Public Inspection on
09/17/2021 at 8:45 am.
It was viewed
4
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2021-20240 (86 FR 52132)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
U.S. Army Corps of Engineers, Department of the Army, DoD.
ACTION:
Notice of intent.
SUMMARY:
The U.S. Army Corps of Engineers (USACE), Seattle District, is announcing its intent to prepare a supplemental environmental impact statement (SEIS) in compliance with the National Environmental Policy Act for the express purpose of addressing updates to the implementation of Howard A. Hanson Dam (HAHD) downstream fish passage to be instituted as part of the Additional Water Storage Project on the Green River in King County, Washington. The SEIS will supplement the
HAHD Additional Water Storage Project Final Feasibility Report and Final EIS
(August 1998) prepared by USACE.
Ms. Nancy Gleason, Environmental Coordinator, 206-764-6577 or Ms. Katherine LaPonte, Project Manager, 206-351-6077; email to
HAHD-fishpassage@usace.army.mil;
or mail to USACE Seattle District, CENWS-PMP-E, P.O. Box 3755, Seattle, WA 98124-3755.
SUPPLEMENTARY INFORMATION:
The USACE, Seattle District, will prepare an SEIS in accordance with 33 CFR 230.13(b) for proposed modifications to the recommended alternative for the downstream fish passage component of the previously authorized HAHD Additional Water Storage Project in King County, Washington. The scope of this SEIS will not extend to other elements of the project related to water supply or ecosystem restoration, as those components were not materially altered from the description evaluated in the 1998 EIS and have already been implemented. The purpose of the fish passage component of the larger
( printed page 52133)
Additional Water Storage Project remains the same as the original EIS: To successfully pass migrating juvenile fish downstream.
The 1998 EIS evaluated a fish passage facility generally consisting of a floating fish collector. In their 2019 Biological Opinion (BiOp) for HAHD operations and maintenance, the National Marine Fisheries Service (NMFS) established survival criteria and transport pipe exit release location criteria that must be met by any fish passage facility for the project. In order to meet these criteria, the USACE has redesigned the downstream fish passage component of the project. In this SEIS, the USACE will evaluate implementation of downstream fish passage via a fixed multiport collection structure that would allow fish collection from a set of five intake ports at multiple elevations as the reservoir water level changes. Once collected through the multiport structure, fish would be transported downstream using one or more steep bypass pipes. The SEIS will evaluate and provide supplemental analysis, as applicable, on any impacts generated by the modification of the downstream fish passage component of the recommended alternative to the quality of the human environment not identified and evaluated in the August 1998 Final EIS. Evaluation may extend, for example, to potential changes in the study area to aquatic habitat, different species listed under the Endangered Species Act (ESA) in the study area, potential changes to the geological analysis associated with the construction of a fish passage facility, potential impacts to natural resources during construction, including elevated noise and disturbance to fish and wildlife at HAHD from rock blasting and operation of construction equipment, potential effects to cultural and historical resources, and temporary effects to water quality and aquatic habitat from construction.
As identified in the original EIS, USACE continues to propose monitoring to determine whether the facility provides safe downstream passage for fish. Once operational, the fish passage facility is expected to have significant benefits to ESA-listed salmonids thereby benefiting the ecosystem of the entire Green River watershed, as well as increasing a primary food source for the endangered Southern Resident killer whales. The anticipated authorizations required prior to construction are expected to include a BiOp from the U.S. Fish and Wildlife Service, a Clean Water Act Section 401 Water Quality Certification, concurrence from the Washington Department of Ecology on a Coastal Zone Management Act Consistency Determination, and consultation under Section 106 of the National Historic Preservation Act.
The draft SEIS will be made available for public and agency review and comment, which is expected to occur in October 2021. After public review of the draft SEIS and evaluation of the comments received, USACE will promulgate a final SEIS; this is expected to occur in 2022.
Comments or questions concerning this proposed action can be directed to the USACE contacts listed above.