This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to
About the Federal Register
on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Proposed Rule
Enter a search term or FR citation e.g.
88 FR 38230 FR 78782024-13208USDA09/05/24RULE0503-AA39SORN
Choosing an item from
full text search results
will bring you to those results. Pressing enter in the search box
will also bring you to search results.
Choosing an item from
suggestions
will bring you directly to the content.
The NRC plans to hold public meetings in March and April 2023 during the 60-day public comment period. See Section III, "Request for Comments and Public Meetings," of this document for more information on the meetings.
Table of Contents
Enhanced Content - Table of Contents
This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.
FederalRegister.gov retrieves relevant information about this document
from Regulations.gov to provide users with additional context. This
information is not part of the official Federal Register document.
Document page views are updated periodically throughout the day and are
cumulative counts for this document. Counts are subject to sampling,
reprocessing and revision (up or down) throughout the day.
Page views
500
as of
09/14/2026 at 4:15 pm EDT
Other Formats
Enhanced Content - Other Formats
This document is also available in the following formats:
This PDF is FR Doc. 2023-04982 as it appeared on Public Inspection on
03/09/2023 at 8:45 am.
It was viewed
10
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.
Published Document: 2023-04982 (88 FR 14958)
This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Proposed rule; public meetings and request for comment.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC) plans to hold comment-gathering public meetings on a proposed rule to amend its environmental protection regulations by updating the Commission's 2013 findings on the environmental effect of renewing the operating license of a nuclear power plant. The purpose of the meetings is to provide information and receive public comments on the proposed changes to NRC regulations, draft Revision 2 to NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants” (LR GEIS), and associated guidance.
DATES:
The NRC plans to hold public meetings in March and April 2023 during the 60-day public comment period. See Section III, “Request for Comments and Public Meetings,” of this document for more information on the meetings.
ADDRESSES:
Please refer to Docket ID NRC-2018-0296 when contacting the NRC about the availability of information regarding this public meeting. You may obtain publicly available information related to this action by any of the following methods:
Federal Rulemaking Website:
Go to
https://www.regulations.gov
and search for Docket ID NRC-2018-0296. Address questions about NRC dockets to Dawn Forder; telephone: 301-415-3407; email:
Dawn.Forder@nrc.gov. For technical questions contact the individuals listed in the
FOR FURTHER INFORMATION CONTACT
section of this document.
Email comments to: Rulemaking.Comments@nrc.gov. If you do not receive an automatic email reply confirming receipt, then contact us at 301-415-1677.
Mail comments to:
Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, ATTN: Rulemakings and Adjudications Staff.
For additional direction on obtaining information and submitting comments, see “Obtaining Information and Submitting Comments” in the
SUPPLEMENTARY INFORMATION
section of this document.
FOR FURTHER INFORMATION CONTACT:
Yanely Malave-Velez, Office of Nuclear Material Safety and Safeguards, telephone: 301-415-1519, email:
Yanely.Malave-Velez@nrc.gov; Jennifer Davis, Office of Nuclear Material Safety and Safeguards, telephone: 301-415-3835, email:
Jennifer.Davis@nrc.gov; or Kevin Folk, Office of Nuclear Material Safety and Safeguards, telephone: 301-415-6944, email:
Kevin.Folk@nrc.gov. All are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2018-0296 when contacting the NRC about the availability of information for this action. You may obtain publicly available information related to this action by any of the following methods:
NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly available documents online in the ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/adams.html. To begin the search, select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to
PDR.Resource@nrc.gov.
NRC's PDR:
You may examine and purchase copies of public documents, by appointment, at the NRC's PDR, Room P1 B35, One White Flint North, 11555 Rockville Pike, Rockville,
( printed page 14959)
Maryland 20852. To make an appointment to visit the PDR, please send an email to
PDR.Resource@nrc.gov
or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time, Monday through Friday, except Federal holidays.
B. Submitting Comments
The NRC encourages electronic comment submission through the Federal rulemaking website (
https://www.regulations.gov). Please include Docket ID NRC-2018-0296 in your comment submission.
The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC will post all comment submissions at
https://www.regulations.gov
as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information.
If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment into ADAMS.
II. Background
On March 3, 2023, the NRC published a proposed rule in the
Federal Register
for a 60-day public comment period (88 FR 13329). The NRC proposes to amend its environmental protection regulations by updating the Commission's 2013 findings on the environmental effect of renewing the operating license of a nuclear power plant in part 51 of title 10 of the
Code of Federal Regulations
(10 CFR), “Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions,” subpart A, “National Environmental Policy Act—Regulations Implementing Section 102(2).” Additionally, the NRC proposes to revise NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants” (LR GEIS), which is intended to streamline the NRC's license renewal environmental review by documenting a systematic approach that the NRC uses to evaluate the environmental impacts of renewing the operating licenses of commercial nuclear power plants. The LR GEIS also provides the technical basis for Table B-1, in appendix B to subpart A of 10 CFR part 51, “Environmental Effect of Renewing the Operating License of a Nuclear Power Plant.” Among other things, these proposals will update 10 CFR part 51 and the LR GEIS to fully account for subsequent license renewal as well as initial license renewal. The NRC will solicit comments at each meeting for consideration in the development of the final rule, LR GEIS, and associated guidance.
III. Request for Comments and Public Meetings
The NRC staff plans to hold the following comment-gathering public meetings during the 60-day public comment period to present an overview of the proposed changes to the environmental protection regulations and the LR GEIS.
○ March 16, 2023, at the Bethesda North Marriott Hotel & Conference Center; First Meeting: Open House from 1:30 p.m.-2 p.m. and Public Meeting from 2 p.m.-4 p.m. (local time).
○ Second Meeting: Open House from 5:30 p.m.-6 p.m. and Public Meeting from 6 p.m.-8 p.m. (local time).
March 28, 2023, at the Marriott Chicago Naperville; 1801 N Naperville Boulevard, Naperville, IL 60563. Open House from 5:30 p.m.-6 p.m. and Public Meeting from 6 p.m.-8 p.m. (local time).
March 30, 2023, at the Marriott Dallas/Ft. Worth Westlake; 1301 Solana Boulevard, Building 3, Westlake, Texas 76262. Open House from 5:30 p.m.-6 p.m. and Public Meeting from 6 p.m.-8 p.m. (local time).
April 4, 2023, at the Alloy King of Prussia; 301 West DeKalb Pike, King of Prussia, Pennsylvania 19406. Open House from 5:30 p.m.-6 p.m. and Public Meeting from 6 p.m.-8 p.m. (local time).
April 6, 2023, at the Courtyard by Marriott Atlanta Decatur Downtown/Emory; 130 Clairemont Avenue, Decatur, GA 30303. Open House from 5:30 p.m.-6 p.m. and Public Meeting from 6 p.m.-8 p.m. (local time).
Interested stakeholders also may attend by telephone or online webinar. The public meetings will be transcribed and will include a presentation of the contents of the draft LR GEIS and proposed rule; and an opportunity for government agencies, organizations, and individuals to provide comments. No oral comments on the draft LR GEIS or proposed rule will be accepted during the open house sessions. To be considered, oral comments must be presented during the transcribed portion of the public meeting. The NRC staff also will accept written comments at any time during the public meetings. Persons interested in presenting oral comments at any of the six public meetings are encouraged to pre-register. Information for the teleconference and online webinar will be available in the meeting notices, which can be accessed through the NRC's Public Meeting Schedule at
https://www.nrc.gov/pmns/mtg.
Members of the public also may register to provide oral comments in-person at each meeting. Individual oral comments may be limited by the time available, depending on the number of persons who register.
If special equipment or accommodations are needed to attend or present information at a public meeting, please contact Yanely Malave-Velez, telephone: 301-415-1519, email:
Yanely.Malave-Velez@nrc.gov,
no later than 10 days before the designated scheduled meeting to provide the NRC staff adequate notice to determine whether the request can be accommodated.
The NRC requests that comments that are not provided during the meeting be submitted as noted in Section I, “Obtaining Information and Submitting Comments,” of this document in writing by May 2, 2023.
IV. Availability of Documents
The documents identified in the following table are available to interested persons through one or more of the following methods, as indicated.
( printed page 14960)
Document
ADAMS
accession No. 1
Federal Register
citation
Proposed Rule: Renewing Nuclear Power Plant Operating Licenses—Environmental Review, March 3, 2023
Draft Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants
Draft NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants,” Volume 1, Revision 2
ML23010A078
Draft NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants,” Volume 2, Revision 2
ML23010A086
Draft Guidance Documents
Draft NUREG-1555, Supplement 1, Revision 2, “Standard Review Plans for Environmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal”
ML22165A070
Draft Regulatory Guide DG-4027, “Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications” (also referenced as Regulatory Guide (RG) 4.2, Supplement 1)
ML22165A072
The NRC may post materials related to this document, including public comments, on the Federal rulemaking website at
https://www.regulations.gov
under Docket ID NRC-2018-0296. The Federal rulemaking website allows members of the public to receive alerts when changes or additions occur in a docket folder. The following actions are needed to subscribe: (1) navigate to the docket folder NRC-2018-0296, (2) click the “Subscribe” link, and (3) enter an email address and click on the “Subscribe” link.
Dated: March 7, 2023.
For the Nuclear Regulatory Commission.
Patricia K. Holahan,
Director, Subsequent License Environmental Directorate, Office of Nuclear Material Safety and Safeguards.